Luneng Haixi 50MW molten salt tower CSP project to operate this June

2019.01.24     From: CSP Focus光略咨询




Located in Haixi, Qinghai Province in Northwest China, Luneng Haixi 50MW Molten Salt Tower CSP Project is a crucial part of 700MW Luneng Haixi Geermu Multi-energy Complement Integration Optimization Pilot Project, which consists of 200MW PV, 400MW Wind, 50MW CSP and 50MW energy storage system.


The annual electricity generation of the Integration Project is expected to be around 1262.5GWh after completion, reducing standard coal consumption of 401,500 metric tons and dust emission of 5431.96 metric tons.


The 50MW CSP plant was started construction on June 30, 2017, and now entering construction peak period in spite of the freezing winter. As the project EPC contractor SEPCOIII Electric Power  Construction Co., Ltd. says to CSP Focus, it is expected to be operational in months this June 2019.


At that time, Luneng Haixi project will be the first large-scale commercial solar thermal power plant which is not amongst China 1st batch of CSP demonstration projects, and predictably the 4th one after CGN Delingha 50MW parabolic trough, Shouhang Dunhuang 100MW molten salt tower, and SUPCON Delingha 50MW molten salt tower CSP projects.



A total number of 4,400 heliostats (138m² per) will be installed in the solar field covering an area of 610000m². The receiver tower will be 181.1 meters high, of which 147.4 meters are made up of reinforced concrete.


Up to date, the 147.4m concrete tower has been completed, and more than 140 heliostats have been installed and commissioned.


The pouring of steam turbine generators concrete foundation has been completed. The overall civil work of the project has been successfully completed; basic construction work on the transformer room of heat storage, chemical water, air cooling is basically finished; the heat storage and transfer system, deaerator and evaporator drum in SGS system have been all in place. The pipeline installation has started now; fire prevention measures on the hot, cold salt tank have been finished, comprehensive construction on which has commenced.


More project details and updates please download the fresh report produced by CSP Focus: 

Free Report: Luneng Haixi 50MW Molten Salt Tower CSP Plant (New)


Milestones of Luneng Haixi 50MW Molten Salt Tower CSP Project:


 ● 2019-6, expected to be operational

 ● 2019-1, civil work completed, equipment installation started

 ● 2018-11-21, construction completion of receiver tower (147.4m of 181.1m)

 ● 2018-10, COD of PV and Wind projects

 ● 2017-6-30, project construction started

 ● 2016-12-26, Project approval from National Energy Administration


In terms of the key equipment and service providers, China SEPCOIII Electric Power  Construction Co., Ltd., who is also the EPC contractor of Morocco NOORo 2&3 projects, work as the turnkey EPC for the project owner--Luneng Group. European leading CSP firms Abengoa and Fichtner act as the roles of Solar field technology provider and Owner's Engineer respectively.


Other overseas companies including CMI, Flowserve, OHL, MICC, Emerson, BCB, Siemens provide some of the key products like molten salt pump and valve, heat tracing, DCS, steam turbine.


Some components are manufactured by Chinese local companies, such as mirrors from Daming, steam generator from Hangzhou Boiler, hydraulics from Sichuan CRUN.


To read the full list of the confirmed vendors for China leading 13 CSP projects including Luneng Haixi 50MW molten salt Tower CSP Plant, please click: 

Free Report: Suppliers List of China Key CSP Projects (Jan. 2019 Edition)   


A giant tent is built up with a volume of 41054.34 cubic meters, to ensure the construction of storage tank in the freezing winter time.





Upcoming CSP events:


9th Annual CSP Focus China 2019(Mar.21-22, Beijing)

4th Annual CSP Focus MENA 2019(Jun.26-27, Dubai)


More CSP news and reports please visit www.cspfocus.cn 

or CSP Focus social media on LinkedInTwitterFacebook


Leave your thoughts here

Reports(Member Only)

See more+
  • CSP Focus Membership Proposals

    We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea

  • The Latest CSP Focus Monthly Update

    Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.

  • CSP Project Monthly Update 2022 December Edition

    CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.

  • Presentations-CSP Focus China 2021

    The Report is for CSP Focus Members only.

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news