China largest parabolic trough CSP plant foresees completion this year
2019.02.19 From: CSP Focus
As one of the first batch of 20 pilot CSP projects, CSNP Royal Tech Urat 100MW Parabolic Trough CSP Project is the largest trough plant within the pilot projects and the only remaining pilot project located in Inner Mongolia province.
With the total investment of around RMB 2.9 billion, the 100MW parabolic trough CSP project is equipped with 375 PT loops and 10 hours' molten salt thermal energy storage system. The annual electricity generation is expected to be 350GWh.
Following
the first CGN Delingha 50MW parabolic trough CSP project which was connected to the grid in October 2018, CSNP Royal Tech Urat 100MW CSP Project is now developed smoothly, and expected to be completed by the end of this year, when it will be the second parabolic trough CSP demonstration project, and also the first 100MW large-scale parabolic trough CSP plant in China.
Milestones of CSNP Royal Tech Urat 100MW Parabolic Trough CSP Project:
● April 11th, 2018, basic engineering almost finished; 80% completion of site leveling
● July 29th, 2017, China Shipbuilding New Power Co., Ltd awarded as EPC contractor
● July 21th, 2017, site leveling started
● November 14th, 2016, evaluation close of project feasibility study
More project details and updates please download the fresh report produced by CSP Focus:
Free Report: CSNP Royal Tech Urat 100MW Parabolic Trough (New)
The 1st batch of 1365 high temperature vacuum receiver tubes have been
sent from Royal Tech Changzhou factory to the Inner Mongolia CSP plant
site in December, 2017.
The major shareholder and EPC contractor of the project is China Shipbuilding New Power Co., Ltd (shorted as CSNP), a state owned enterprise with strong commitment in CSP. The project co-investors are China Nuclear (Nanjing) Energy Development Co., Ltd and Royal Tech CSP Limited.
The
collector technology - optimized EuroTrough - which is licensed by Schlaich Bergermann Partner (sbp), will be applied in the project, and
it is the second pilot project taking this technology after CGN Solar Delingha 50MW
PT Project.
As the crucial players in this 100MW CSP project, CSNP, Royal Tech CSP and sbp will all be attending CSP Focus China 2019 Mar.21-22 Beijing conference, during which you may meet and discuss with them regarding the project details face-to-face.
Overseas companies including Flowserve, Rioglass, Siemens, Hyspan
provide some of the products like pump, mirror, steam turbine, and ball joints. More components are manufactured by Chinese local
companies, such as HTF oils from Jiangsu Zhongneng and The 718th research institute of China Shipbuilding Industry Corporation, and Heat Exchanger (Oil-Salt) from Wuxi Chemical Equipment.
To
read the full list of the confirmed vendors for China leading 13 CSP projects
including CSNP Royal Tech Urat 100MW Parabolic Trough CSP Project, please
click:
Free Report: Suppliers List of China Key CSP Projects (Jan. 2019 Edition)
Upcoming CSP events:
9th Annual CSP Focus China 2019(Mar.21-22, Beijing)
4th Annual CSP Focus MENA 2019(Jun.26-27, Dubai)
More CSP news and reports please visit www.cspfocus.cn
or CSP Focus social media on LinkedIn, Twitter, Facebook.
More from CSP Focus
Next247SOLAR CEO BRUCE ANDERSON TO INTRODUCE NEXT GENERATION LOW-COST CSP
Iberdrola looking to sell 50-MW Spanish Concentrated Solar Power plant
How Did Cosin Solar Tower CSP Reach Projected Performance So Fast?
Spanish CSP plants increase output by 8% y/y in Jan-May 2019
Stanwell signs up to Vast Solar’s Mt Isa Concentrated Solar Power project
Chinese EPC consortium of Greece MINOS 50MW CSP Project look for partners and vendors
Full capacity test a success for concentrated solar power plant in China
Aalborg CSP secures flat panel order for industrial solar heating plant in Denmark
Leave your thoughts here
Reports(Member Only)
See more+-
CSP Focus Membership Proposals
We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea
-
The Latest CSP Focus Monthly Update
Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.
-
CSP Project Monthly Update 2022 December Edition
CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.
-
Presentations-CSP Focus China 2021
The Report is for CSP Focus Members only.
Upcoming Events
See more+-
12th CSP Focus China 2022
2022.04.21-22 Beijing
-
11th CSP Focus China 2021
2021.10.28-29 Beijing
-
10th CSP Focus China 2020
2020.10.22-23 Beijing, China
Project Updates
See more+-
Lanzhou Dacheng Dunhuang CSP Project
Asia Pacific-China,Operational,Parabolic Trough
-
Luneng Haixi 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower
-
Dubai 950MW NOOR Energy 1 CSP+PV Project
MENA-UAE,Under construction,Power Tower
-
Power China Gonghe 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower