Dubai CSP suppliers tested on durability for longest-ever PPA (35 years)

2019.03.15     From: newenergyupdate

Suppliers to ACWA Power’s 950 MW Noor Energy 1 plant are using enhanced strength and design features to ensure reliability throughout the 35-year power purchase agreement (PPA), the companies told New Energy Update.


EPC group Shanghai Electric has probed the durability of CSP systems on Noor Energy 1 to meet record-long offtake requirements. 


A flurry of recent supply contracts for ACWA Power’s 950 MW Noor Energy 1 CSP-PV plant in Dubai signals accelerating activity on the world’s largest CSP construction project.


The $4.4 billion Noor Energy 1 project includes three 200 MW parabolic trough systems supplied by Spain’s Abengoa, a 100 MW central tower plant supplied by U.S. developer BrightSource and 250 MW of PV capacity.


China’s Shanghai Electric Corporation (SEC) is the lead EPC Contractor for the project, which will host 15 hours of molten salt CSP storage capacity and be brought online in phases in 2020-2022.


Last month, Spain’s Lointek signed a contract to supply the integrated steam generation system and oil salt thermal storage system for the 700 MW CSP plant section. Lointek will engineer, manufacture, install and commission the power island under a turnkey contract.


In January, Germany’s Siemens announced it would supply four steam turbine generators and auxiliary equipment for the parabolic trough and tower plants.


Denmark’s Aalborg CSP has also signed a contract to supply its header-and-coil steam generation technology for the 600 MW parabolic trough section.


The Dubai Electricity and Water Authority (DEWA) awarded the Noor Energy 1 project at a record low tariff of $73/MWh.


Economies of scale, an optimized combination of technology and a record long 35-year power purchase agreement (PPA) helped lower project costs, project partners said.


The 35-year PPA is over 10 years longer than typical arrangements, spreading the initial investment across a longer period and reducing the annual cost of capital.


To meet the longer contracted term, SEC has placed extra demands on suppliers to demonstrate technology durability, the companies told New Energy Update.


Longer lifespan


Until the Noor Energy 1 deal, the average length of PPAs for active CSP projects was 23.8 years, with the longest reported at 25 years, according to New Energy Update’s Global CSP Tracker.


Suppliers to Noor Energy 1 had to demonstrate long-term durability levels conform with Shanghai Electric’s project reliability and insurance requirements.


“To support the lifetime of 35 years, all suppliers had to confirm and calculate fatigue requirements,” Svante Bundgaard, CEO of Aalborg CSP, told New Energy Update.


Abengoa will incorporate recent structural enhancements on its parabolic trough technology to ensure long-term durability, Ana Cristina Gonzalez de Una, Director of business development, Energy at Abengoa, said. Abengoa will supply technology similar to the recently-commissioned 100 MW Xina project in South Africa and 50 MW CSP element of the Waad Al Shamal ISCC plant in Saudi Arabia.


“The most evident enhancement is an increase in the thickness of the galvanised steel structure of the collector,” Gonzalez de Una said.



Source: International Renewable Energy Agency’s ‘Power to Change’ report (2016).


The output profile of CSP plants requires generation system components to accommodate frequent system starts and stops.


“Given the nature of CSP operations, it is essential that the steam turbines used in these plants be highly efficient and offer rapid start-up times,” Siemens said in a statement in January.


Aalborg’s header-and-coil steam generation system meets the long-term reliability requirements as it absorbs thermal dynamic stress, avoiding leaks and reducing downtimes, Bundgaard said.


The 100% welded coil design is based on steam boiler technology already proven in conventional power plants, he said.


Showcase project


SEC is one of China’s top five power generators and has a total installed capacity of over 107 GW, including 5 GW of solar power and 10 GW of wind.


The Noor Energy 1 project is SEC’s first CSP project outside of China. The company is currently acting as co-EPC with BrightSource Energy in China to build the 270 MW Huanghe Delingha CSP Generation tower project.


China is forecast to install 1.9 GW of new CSP plants by 2023, almost half of new global capacity, the International Energy Agency (IEA) said in a report in October.



Forecast global CSP installations

Source: International Energy Agency (IEA), October 2018.


SEC has imposed a collaborative approach to cost optimisation for Noor Energy 1, suppliers told New Energy Update.


“SEC has worked very hard to reduce cost by optimization with key suppliers asking for inputs and ideas,” Bundgaard said.


“This open and cooperative approach has secured them many cost reductions both in terms of direct capex, efficiencies and installation schedule,” he said.


“SEC is a massive group with vast experience in power plants and manufacturing which brings value to the project and to the cooperation between the two companies,” Gonzalez de Una said.


Supplier magnet


The 700MW CSP capacity of the project is almost double the capacity of the 392 MW Ivanpah plant in California, the world’s largest CSP plant currently in operation.


Project partners are using economies of scale and low-cost Chinese manufacturing learnings to drive down costs.


“The large scale of the project helps to reduce component prices because there are more suppliers interested in entering the industry,” Gonzalez de Una said.


The large project also presents opportunities for innovative manufacturing and automation processes, she said.


Site logistics is one of the greatest challenges for suppliers, Gonzalez de Una said. The company estimates more than 30 containers per day will arrive at the site, requiring optimized planning of storage, transportation and port facilities.


“Everything needs to be perfectly synchronized,” she said.


Logistics challenges have been heightened by an accelerated construction schedule.


Under a revised plan, the first parabolic trough plant and the central tower unit are scheduled to be completed before the Expo 2020 Dubai takes place in October 2020, six months earlier than the previously-announced target.


Upcoming CSP events:


9th Annual CSP Focus China 2019(Mar.21-22, Beijing)

4th Annual CSP Focus MENA 2019(Jun.26-27, Dubai)


More CSP news and reports please visit www.cspfocus.cn 

or CSP Focus social media on LinkedInTwitterFacebook

Leave your thoughts here

Reports(Member Only)

See more+
  • CSP Focus Membership Proposals

    We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea

  • The Latest CSP Focus Monthly Update

    Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.

  • CSP Project Monthly Update 2022 December Edition

    CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.

  • Presentations-CSP Focus China 2021

    The Report is for CSP Focus Members only.

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news