China Luneng Haixi 50MW Tower CSP project to operate end August

2019.07.30     From: CSP Focus光略咨询


Located in Haixi, Qinghai Province in Northwest China, Luneng Haixi 50MW Molten Salt Tower CSP Project is a crucial part of 700MW Luneng Haixi Geermu Multi-energy Complement Integration Optimization Pilot Project, which consists of 200MW PV, 400MW Wind, 50MW CSP and 50MW energy storage system.




The 50MW CSP plant, namely Luneng Haixi 50MW Molten Salt Tower CSP Project was started construction on June 30, 2017, and now entering commissioning period before its completion . Mr. ZENG Xuyao, Deputy General Manager of the Project Developer Luneng Qinghai Geermu New Energy Company reported recently on the project progress, saying it is expected to be operational in one month by the end of this August.


At that time, Luneng Haixi project will be the first large-scale commercial solar thermal power plant which is not amongst China 1st batch of CSP demonstration projects, and the 4th CSP plant in China after CGN Delingha 50MW parabolic trough, Shouhang Dunhuang 100MW molten salt tower, and SUPCON Delingha 50MW molten salt tower CSP projects which were connected to the grid last year in 2018.



A total number of 4,400 heliostats (138m² per) will be installed in the solar field covering an area of 610000m². The receiver tower will be 181.1 meters high, of which 147.4 meters are made up of reinforced concrete.


More project details and updates please download the fresh report produced by CSP Focus: 

Free Report: Luneng Haixi 50MW Molten Salt Tower CSP Plant (July 2019 Edition)


Milestones of Luneng Haixi 50MW Molten Salt Tower CSP Project:


 ● 2019-8-30, expected to be operational

 ● 2019-7-4, Steam turbine and generator installed

 ● 2019-4-30, 2,100 heliostats installed (4,400 in total)

 ● 2019-1-2, civil work completed, equipment installation started

 ● 2018-11-21, construction completion of receiver tower (147.4m of 181.1m)

 ● 2018-10, COD of PV and Wind projects

 ● 2017-6-30, project construction started

 ● 2016-12-26, Project approval from National Energy Administration



In terms of the key equipment and service providers, China SEPCOIII Electric Power Construction Co., Ltd., who is also the EPC contractor of Morocco NOORo 2&3 projects, work as the turnkey EPC for the project owner--Luneng Group. European leading CSP firms Abengoa and Fichtner act as the roles of Solar field technology provider and Owner's Engineer respectively.


Other overseas companies including HP Valves, Flowserve, Eltherm, OHL, CMI, MICC, Emerson, BCB, Siemens provide some of the key products like molten salt pump and valve, heat tracing, DCS, steam turbine.


Some components are manufactured by Chinese local companies, such as thermal insulation from Luyang, mirrors from Daming, steam generator from Hangzhou Boiler, hydraulics from Sichuan CRUN.


To read the full list of the confirmed vendors of Luneng Haixi 50MW molten salt Tower CSP Plant, please click: 

Free Report: Luneng Haixi 50MW Molten Salt Tower CSP Plant (July 2019 Edition)



And you are also welcome to join the upcoming 3rd CSP Focus Innovation 2019(Oct.24-25, Beijing China)  conference and expo, where the project developer Luneng and technology provider Abengoa are expected to be present, sharing the fresh updates and experience on Luneng Haixi CSP Project.


Click here to get the event brochure and register BEFORE Aug.1 will SAVE you USD200/per.






Upcoming CSP event:


3rd CSP Focus Innovation 2019(Oct.24-25, Beijing China)

10th CSP Focus China 2020 (March, Beijing China) 


More CSP news and reports please visit www.cspfocus.cn 

or CSP Focus social media on LinkedInTwitterFacebook.


Leave your thoughts here

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news