中文  |  ENGLISH

Centrifugal Concentrated Solar Power could offer siting breakthroughs, $60/MWh power

2019.07.31     From: newenergyupdate

A new ceramic particle Concentrated Solar Power receiver soon to be tested in the U.S. could lower the cost of energy by up to 20% and accelerate industrial heat deployment through particle transport innovations, Reiner Buck, Head of Solar Tower Systems at German Aerospace Centre (DLR), told New Energy Update.



DLR’s 1000° C direct absorption particle receiver offers benefits for power and heat applications. (Image credit: DLR)


Last month, the U.S. Department of Energy allocated $750,000 of funding to Sandia National Laboratories to accelerate testing of the centrifugal receiver (Centrec), a new high-temperature ceramic particle receiver developed by the German Aerospace Center (DLR).


Current CSP tower plants use molten salt as the heat transfer medium (HTM) and storage media, limiting temperatures to 565°C to avoid corrosion and decomposition. A number of research groups are developing systems that achieve higher temperatures and increase the efficiency of converting heat to electricity.


DLR will use Sandia’s National Solar Thermal Test Facility (NSTTF), in Albuquerque, New Mexico, to demonstrate the Centrec concept can reach particle temperatures of over 1,000° C at the receiver outlet. Two earlier demonstration phases at DLR’s Julich Solar Tower test facility achieved particle temperatures of 965 °C.


Power efficiency and energy storage gains from larger temperature ranges and lower density design requirements creates significant advantages for Centrec over molten salt technology, Buck told New Energy Update.


“Preliminary estimations show us that going to higher temperatures from the particle side results in a cost reduction between 10 to 20%,” he said.


New limits


CentRec uses a rotating receiver placed atop the tower which exerts centrifugal force to keep dark bauxite particles a sand-like material– in motion along the chamber wall. This allows direct irradiation of the particles from the solar flux.


Bauxite can achieve an operational temperature range of around 600°C, operating between 400° C and 1000° C, double the range (290 to 565°C) attainable by molten salt systems.


“The main advantages compared to existing technologies are that we can go up to significantly higher temperatures, maintaining high receiver efficiencies and achieving relatively low receiver costs,» Buck said.


       Impact of HTM temperature range on CSP component costs

Source: Reiner Buck, 2018.


The Centrec concept would likely favor a multi-tower design to attain the capacity offered by current CSP projects, typically over 100 MW.


DLR modelled a steam turbine power cycle in a 125 MWe multi-tower (14 modules) with 12-hours of storage and bauxite particles as HTF and storage medium. Cost savings associated with low particle inventories (due to minimal corrosion), storage containment and the steam generator significantly reduced LCOE, the researchers said.


Unlike molten salts, ceramic particles are not liable to freezing, requiring less anti-freeze measures for tubes and components.


The higher driving temperature difference in the heat exchanger allows a smaller heat exchanger design, and direct irradiation of the particles avoids the need for costly superalloy tubes used for conventional liquid concepts.


The Centrec concept also lowers the cost of energy storage, a key driver of commercial CSP deployment.


The expanded temperature range of bauxite particles can double the storage density of the solar salt system, Buck said. The researchers estimate the cost of the storage system at 9.2 euros/kWh (around $10/kWh), less than half of the cost of a molten salt storage system.


The overall cost savings are partially offset by higher costs for the heliostat field and towers. The design requires a reduction in receiver efficiency, requiring more heliostats and a taller tower.


Taking these factors into account, Buck’s team estimates that using a 600° temperature difference between receiver inlet and exit can achieve an LCOE of 56 euros/MWh (around $60/MWh).


              Impact of CSP receiver temperature range on LCOE

Source: Reiner Buck, 2018.


Key challenges for the deployment of falling particle receiver systems include maintaining a constant and sufficient mass flow rate of particles at larger scales, plant reliability for a large rotating receiver system and parasitic energy requirements.


The Centrec partners are implementing a range of projects to tackle these issues, covering areas such as up-scaling, long term operation experience and high flux/high mass flow operations, he said.


One of the main technical risks to commercial viability is the potential degradation of structural materials due to abrasion, Buck said.


«However, in many parts of the system this can be influenced by design parameter (flow velocity, …),» he said.


Following successful testing and scaling up of the design in the coming years, the Centrec concept could potentially be deployed on commercial projects towards the end the 2020s.


Before then, the concept could be used to reduce emissions and drive up energy efficiency in the industrial heat sector. The design could reach market readiness for heat process applications within the next five years, the researchers said.


Heating gains


The CentRec system allows the transport of heated particles over several kilometres, expanding siting opportunities for heat applications and multi-tower configurations.


Instead of using a pipe network, the researchers propose using autonomous trucks to transport insulated containers of particles from the individual towers to the steam cycle power block over 1 km away.


Preliminary cost estimations show this process incurs a minimal cost increase, «in the few percent range,” Buck said.


This transportation capability could improve the feasibility of fitting CSP systems to existing process heat facilities at industrial sites.


“A factory which requires a lot of high temperature process heat often does not have useful space directly aside the facility so you can move the solar plant around 1 km away,” Buck said.


This could be a game changer in the Chilean mining industry, where DLR is actively seeking partners for dual heat and power projects.


Dust accumulation around facilities in the Atacama Desert is a barrier to CSP deployment, Buck said.


“Moving the solar facility a certain distance might be a benefit with regards to dust contamination of the heliostat field,” he said.


Upcoming CSP event:


3rd CSP Focus Innovation 2019(Oct.24-25, Beijing China)

10th CSP Focus China 2020 (March, Beijing China) 


More CSP news and reports please visit www.cspfocus.cn 

or CSP Focus social media on LinkedInTwitterFacebook.


Leave your thoughts here

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news