China pilot CSP plant progress—SunCan Dunhuang 100MW tower project to operate by Aug. 2018

2017.06.21     From: CSP Focus

10 months have passed since China government launched the first batch of 20 CSP pilot projects announced last September. As the first molten salt tower plant starting construction, SunCan Dunhuang 2nd Phase 100MW molten salt tower CSP plant catches the eyes of CSP industry players.

Mr. Huang Wenbo, Vice President and Deputy GM of Shouhang IHW Resources Saving Technology Co., Ltd, the developer of the project, spoke and introduced the latest progress and expectations of the project last week.

Timeline--SunCan Dunhuang 2nd Phase 100MW molten salt tower CSP plant:

November 2016, officially started construction;
June 10th 2017, the tower has been built up to 100 meters, and will be soon completed by the end of August, 2017;
March 2018, all the construction and installation of solar concentrating and receiving system will be completed;
  (
Note: heliostats will be assembled, tested and installed in September 2017, and the construction and installation of mirror field will be completed by January 2018, which means only 5 months will be taken for the heliostat construction.)
August, 2018, the project will be put into operation.

Mr. Huang expressed confidence in finishing the plant construction by August 2018. Based on the experience in constructing and commissioning the first phase 10MW project which operated successfully in December 2016, Shouhang is able to make an accurate forecast on the construction so as to fulfill time requirements.

About 70% of the products and materials are produced by Shouhang itself under its big data intelligent manufacturing lines; Some long- procurement-cycle outsourcing components have already been ordered earlier, and some of the time-consuming steps also have been taken into thorough consideration.

According to project experience and feature, Shouhang also developed a 5D management software, which is a platform to conduct transparent and visual management including 3D digitization of engineering and design, resource allocation, project schedule, cost budget, accounting, fund dispatch etc., making the entire project construction more scientific and orderly.

The following pictures show the construction process of SunCan Dunhuang 2nd Phase 100MW molten salt tower CSP plant:









Leave your thoughts here

Reports(Member Only)

See more+
  • CSP Focus Membership Proposals

    We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea

  • The Latest CSP Focus Monthly Update

    Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.

  • CSP Project Monthly Update 2022 December Edition

    CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.

  • Presentations-CSP Focus China 2021

    The Report is for CSP Focus Members only.

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news