中文  |  ENGLISH

Home > Market > China > Here

Three concentrated solar power projects of 335MW “rescued” in China

2020.03.10     From: CSP Focus

China government launched the first batch of 20 demonstration CSP project s in September 2016, and seven of the twenty were successively connected to the grid in the past two years. Meanwhile, 13 of the demos are not complete and some even announced cancellation.


As CSP Focus keeps reporting, CSP industry players are trying to “rescue” the “dead” projects. Three of the cases are made by two Chinese leading CSP project developers and EPCs---Shouhang High-Tech and SUPCON Solar, both of whom already built up CSP tower plants of their own.


Shouhang High-Tech continuously took over Guohua Yumen 100MW Molten Salt Tower Project and China Three Gorges New Energy Jinta 100MW Molten Salt Tower Project, and expected to complete them in two years by 2021.


SUPCON Solar told CSP Focus that Huanghe Hydropower Development 135MW Molten Salt Tower Project was already transferred to SUPCON and will be restarted soon.


Chart: Status of China 1st Batch of 20 Demonstration CSP Projects


(Click to enlarge the pictures)


Part I. Status of 7/20 operational China first batch of demonstration CSP projects


Chart: China Large-scale Commercial CSP Projects in Operation


(Click to enlarge the picture)


1. CGN Solar Delingha 50MW Parabolic Trough CSP Project (9h TES)



China first large-scale CSP project which was connected to the grid on June 30, 2018 and officially operational on October 10, 2018. It achieved daily output of 800 MWh on April 16, 2019. It is the only finished CSP project taking parabolic trough technology.


2. Shouhang Dunhuang 100 MW Molten Salt Tower CSP Project (11h TES)



China first 100MW level CSP project and first large-scale molten salt tower CSP plant which was completed on December 28, 2018. It achieved daily output of 1,800 MWh on June 17, 2019.


3. SUPCON Solar Delingha 50MW Molten Salt Tower CSP Project (7h TES)



The third CSP demonstration project in China starting operation on December 30, 2018. The monthly generation reached record high at 17.1795 GWh in February 2020 (from Jan 26 to Feb 25), with the generation fulfillment rate of 102.9%.


Latest news: China Supcon Delingha 50MW CSP plant achieved record high performance in Feb. 2020.


4. Power China Gonghe 50MW Molten Salt Tower CSP Project (6h TES)



The project was connected to the grid on September 19, 2019.


5. CPECC Hami 50MW Molten Salt Tower CSP Project



The project was successfullly connected to the grid at 23:39 p.m. on December 29th, 2019.


6. Lanzhou Dacheng Dunhuang 50MW Molten Salt Fresnel Project




The project was successfullly connected to the grid at 17:50 p.m. on December 31, 2019, becoming the first demonstration Fresnel CSP project in China, and the world largest solar thermal power plant taking Fresnel CSP technology.

7. CSNP Royal Tech Urat 100MW Parabolic Trough CSP Project




The project was connected to the gird at 22:49 p.m. on January 8th, 2020, becoming the second parabolic trough CSP demonstration project, and the first 100MW large-scale parabolic trough CSP plant in China.


Get fully learned of the current situation of China 1st batch of CSP demos and other projects, you may:

free download the 24-page report on China Large-scale CSP Projects Update (Jan-2020 Edition).



Part II. Status and future of 13/20 uncompleted China first batch of demonstration CSP projects
 


1. Yumen Xinneng 50MW Beam-down Molten Salt Tower CSP Project


Installation and commissioning of solar field in Module 1 was completed, and installation of solar field in Modules No.2-10 is still in progress. No.1-3 Modules are expected to be completed and connected to the grid in 2020.


2. Royal Tech Yumendongzhen 50MW Parabolic Trough Project


EPC contract signed with Shouhang High-Tech Energy Co., Ltd. on June 2018. Construction is expected to be fully started after receiving clear policy.


3. Guohua Yumen 100MW Molten Salt Tower Project


The project announced cancellation after long time postpone of the bidding of EPC contractor, which was supposed to release in early 2017. But lot of investment of infrastructure and fundamental work had been done by the project company and local government together.


With strong commitment and support from local government of Yumen City of Gansu Province, Shouhang High-Tech Energy Co., Ltd. took over the project ownership and held feasibility study meeting on Dec 23, 2019.


4. China Three Gorges New Energy Jinta 100MW Molten Salt Tower Project


Shouhang High-Tech Energy Co., Ltd announced to take over the project ownership on Feb. 21, 2020, and hopefully complete the project by the end of 2021.


Latest news: Shouhang bags another 100MW CSP Tower project in China.



5. Dahua Shangyi 50MW Molten Salt Tower Project


The project was planned to use DSG tower technology originally, and changed to MS tower technology later.


Shouhang High-Tech Energy Co., Ltd. bought out the share of the project from some individual investors and took 49% of equity of the project recently. And Shouhang will also act as the EPC contractor of the project.


6. Rayspower Yumen 50MW Parabolic Trough Project


Early-stage work has been completed. The owner Rayspower signed Agreement with Shanghai Electric in 2018 to jointly progress the project.


7. Northern United Power Urat 50MW CLFR Project


Inner Mongolia Urat Company took over the project, changing the technology route into Prabolic Trough, and held feasibility study meeting in October, 2019.


8. Huanghe Hydropower Development 135MW Molten Salt Tower Project


SUPCON Solar took over the project and will be restarted soon.


9. Zhongyang Zhangjiakou Chabei 64MW Parabolic Trough Project


Early-stage work has been completed.


10. Shenzhen Jinfan Akesai 50MW Molten Salt Parabolic Trough Project


Part of financing and procurement work has been done, but the construction was paused due to financing problem. The developer is seeking for investment support.


11. Huaqiang Zhaoyang Zhangjiakou DSG 50MW CLFR Project


No progress.


12. CECIC Gansu Wuwei Solar Power Gulang 100MW Parabolic Trough Project


No progress.


13. CITIC Zhangbei DSG 50MW CLFR Project


Supposed to be cancelled.


Get fully learned of the current situation of China 1st batch of CSP demos and other projects, you may:

free download the 24-page report on China Large-scale CSP Projects Update (Jan-2020 Edition).




Upcoming CSP events:


5th CSP Focus MENA 2020(June.23-24,Dubai, UAE)

10th CSP Focus China 2020 (Beijing China) 


More CSP news and reports please visit www.cspfocus.cn 

or CSP Focus social media on LinkedInTwitterFacebook.


Leave your thoughts here

Reports(Member Only)

See more+
  • CSP Focus Membership Proposals

    We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea

  • The Latest CSP Focus Monthly Update

    Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.

  • CSP Project Monthly Update 2022 December Edition

    CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.

  • Presentations-CSP Focus China 2021

    The Report is for CSP Focus Members only.

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news