Dubai's CSP energy build continues progress amidst COVID-19
2020.05.13 From: businesschief
While COVID-19 has impacted millions of organisations around the world, ‘the world’s largest CSP’ build has maintained progress amidst challenging times.
The 700MW concentrating solar power (CSP) plant Known as project Noor Energy 1 is, “the largest single-site concentrated solar power plant in the world, using a state-of-the-art combination of a central tower and parabolic trough concentrated solar power (CSP) technologies to collect energy from the sun,” commented ACWA Power.
“The US$4.4 billion project, which will be the world's largest CSP plant, includes a 100 MW-central tower plant (CT), three 200 MW-parabolic trough (PT) plants and 250 MW of photovoltaic (PV) capacity,” said Worley in a company statement.
This CSP plant is being built for the Dubai Electricity and Water Authority (DEWA), by a consortium between DEWA and ACWA Power - who has led the consortium since being awarded the project in 2017. This plant aims to support the Dubai Clean Energy strategy 2050 to increase the share of clean energy at Dubai to 25% by 2030, and will save 1.6mn tons of CO2.
Despite the current impact the outbreak of COVID-19 is having on organisations around the world, the construction of the Noor Energy 1 project is progressing despite the disruption the outbreak has caused.
In order to minimise labour, schedule and budget disruption, contractors from Spain, CHina, Belgium, Denmark and the US have rallied together, implementing measures to keep workers that are on-site safe and those working from home well connected.
To ensure that work could continue, Shanghai Electric - the projects EPC for Noor Energy 1 - as well as the construction subcontractor partners, have implemented a specialist virus prevention and control procedure alongside supplying PPE to all workers. In addition, due to global travel restrictions limiting staff movement Shanghai Electric has provided local workers for the project.
Alongside new measures to create a safe working environment for construction workers, design and engineering workers provided by Worley, have been largely unaffected due to their ability to work remotely. The consulting firm that is providing engineering, technology and technical review support to the Noor Energy 1 project, has been able to adapt its service as COVID-19, by connecting its workers through videoconferencing and regular project meetings.
“It’s a credit to every stakeholder involved that this strategically important project has progressed minimising schedule impacts despite facing significant logistical, staffing and supply chain challenges,” commented Gilein Steensma, Vice President EMEA, Energy Transition, Worley.
“It is a real testament to the commitment of the UAE to lead on the energy transition and showcases the combination of geographical distribution and strong capabilities of the contractors and subcontractors to adapt their approach to work around COVID-19 on what was already a technically challenging build,” Steensma concluded.
Upcoming CSP events:
10th CSP Focus China 2020 (June 18-19, Beijing China)
5th CSP Focus MENA 2020(September 9-10,Dubai, UAE)
More CSP news and reports please visit www.cspfocus.cn
or CSP Focus social media on LinkedIn, Twitter, Facebook.
More from CSP Focus
NextAmerica’s Concentrated Solar Power Companies Have All but Disappeared
Capex of modular Concentrated Solar Power plants could halve if 1 GW deployed
Tough work to turn the bucket: Aalborg CSP's order book abounds again
Largest concentrated solar plant in Africa reducing Morocco's dependency on external power
Hi-Temp Concentrating Solar Power On Mars!? Tell Us Why — Or Why Not (CT Exclusive Interview)
Solar Impulse 2 soars over Gemasolar, Sener’s Solar Thermal Plant in Seville
Aalborg CSP receives order for integrated heat pump system for district heating plant in Denmark
Concentrated Solar Power towers’ impact on birdlife lower than expected
Leave your thoughts here
Reports(Member Only)
See more+-
CSP Focus Membership Proposals
We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea
-
The Latest CSP Focus Monthly Update
Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.
-
CSP Project Monthly Update 2022 December Edition
CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.
-
Presentations-CSP Focus China 2021
The Report is for CSP Focus Members only.
Upcoming Events
See more+-
12th CSP Focus China 2022
2022.04.21-22 Beijing
-
11th CSP Focus China 2021
2021.10.28-29 Beijing
-
10th CSP Focus China 2020
2020.10.22-23 Beijing, China
Project Updates
See more+-
Lanzhou Dacheng Dunhuang CSP Project
Asia Pacific-China,Operational,Parabolic Trough
-
Luneng Haixi 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower
-
Dubai 950MW NOOR Energy 1 CSP+PV Project
MENA-UAE,Under construction,Power Tower
-
Power China Gonghe 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower