Morocco NoorII CSP project fused salt tank installation finished

2017.11.29     From: SEPCOIII Electric Power Construction Corporation



On November 23th, 2017, Morocco Noor II project fused salt tank installation work was finished. Until now, Noor II #2 cold tank filling salt work was completed 23%, #2 hot tank hydrostatic test was completed, #1 cold tank filling salt work in progress, #1 hot tank filling water work completed 25%.


Noor II project had four salt tanks, two cold tanks and two hot tanks. Each hot tank weighs is 859.5T, each cold tank weighs is 868.9T, the diameter of each molten salt tank is 44.1 meters, the effective volume is 23089 cubic meters and the water pressure is 22488 cubic meters.


The project carefully arranged and guidance, specifically set up a melting salt tank special construction team to promote the construction of molten salt tank to ensure that the tank installation work finished successfully. Among them, Weld seam of # 1 hot tank SW01 and SW02 is a difficult task in welding construction. The project department completed the project with high quality and efficiency in one month and won the high praise and recognition from the owners AWCA and SENER.


Source: SEPCOIII Electric Power Construction Corporation

Leave your thoughts here

Reports(Member Only)

See more+

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news