Morocco NoorII CSP project fused salt tank installation finished
2017.11.29 From: SEPCOIII Electric Power Construction Corporation
On November 23th, 2017, Morocco Noor II project fused salt tank installation work was finished. Until now, Noor II #2 cold tank filling salt work was completed 23%, #2 hot tank hydrostatic test was completed, #1 cold tank filling salt work in progress, #1 hot tank filling water work completed 25%.
Noor II project had four salt tanks, two cold tanks and two hot tanks. Each hot tank weighs is 859.5T, each cold tank weighs is 868.9T, the diameter of each molten salt tank is 44.1 meters, the effective volume is 23089 cubic meters and the water pressure is 22488 cubic meters.
The project carefully arranged and guidance, specifically set up a melting salt tank special construction team to promote the construction of molten salt tank to ensure that the tank installation work finished successfully. Among them, Weld seam of # 1 hot tank SW01 and SW02 is a difficult task in welding construction. The project department completed the project with high quality and efficiency in one month and won the high praise and recognition from the owners AWCA and SENER.
Source: SEPCOIII Electric Power Construction Corporation
More from CSP Focus
NextCapex of modular Concentrated Solar Power plants could halve if 1 GW deployed
15GW CSP projects to compete for China 2nd batch pilot projects
Morocco shortlists 5 consortia for 800MW Noor Midelt solar hybrid CSP & PV project
Concentrated Solar Power reaches 796 GWh generated in July in Spain, 10% more than last year
Leave your thoughts here
Reports(Member Only)
See more+-
CSP Focus Membership Proposals
We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea
-
The Latest CSP Focus Monthly Update
Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.
-
CSP Project Monthly Update 2022 December Edition
CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.
-
Presentations-CSP Focus China 2021
The Report is for CSP Focus Members only.
Upcoming Events
See more+-
12th CSP Focus China 2022
2022.04.21-22 Beijing
-
11th CSP Focus China 2021
2021.10.28-29 Beijing
-
10th CSP Focus China 2020
2020.10.22-23 Beijing, China
Project Updates
See more+-
Lanzhou Dacheng Dunhuang CSP Project
Asia Pacific-China,Operational,Parabolic Trough
-
Luneng Haixi 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower
-
Dubai 950MW NOOR Energy 1 CSP+PV Project
MENA-UAE,Under construction,Power Tower
-
Power China Gonghe 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower