Recently some media, such as Energyskeptic, falsely accused CSP technology of being unreliable, full of glitches and having a low energy return. Their opinion refers to certain early development faults of the technology, mainly based on the US experience, where new CSP stations have not been built since 2015. 


Indeed, all power production technologies have their drawbacks, and we must have the full picture when considering different options. In the upcoming energy transition to zero emissions, dispatchable renewables are critical to ensure electricity security, and requires the massive deployment of all available clean energy technologies. Thus, it is unwise to discard a renewable energy technology, which could provide 24/7 power supply, especially in view of climate change urgency, only based on past problems in single stations. 


Currently there are two main reasons for the performance (and therefore Capacity Factor) decreases in CSP tower plants (for more detailed reasons please check the report of NREL):

1. The leakage of molten salt tank. Molten salt tank leaks have occurred in three solar tower CSP projects, such as Crescent Dunes (USA), Gemasolar (Spain), and NOOR3 (Morocco). Until the leak was stopped, generation had to stop too. 

2. The steam turbine problems, which were especially noticeable among the Chinese CSP projects, but mainly due to the lack of experience in developing such a turbine.


The above issues are mostly related to engineering and chemistry: it is far from trivial to handle molten salt at very high temperatures, and it puts great strain on materials and systems. As demonstrated by the good track record of almost all salt tower stations, these difficulties are manageable. China has a rich experience in design and construction of molten salt tanks due to its previous experience in chemical engineering. Cosin Solar had its first 10 MW power plant with molten salt storage connected to the grid already in 2016, adding later two more 50 MW each power plants and none of them had leakage. In fact, no solar tower project in China has had a problem with molten salt leakage. 


To better communicate the up to date data and decrease the misinformation about CSP, Cosin Solar - the technology provider and operator of the three commercial solar tower plants with experience of more than ten years of plant operation, - will provide its own recent data to counter misgivings about some drawbacks of CSP plant commonly cited by the media.


Starting with the capacity factor (CF) of a CSP plant, which is often criticized for being lower than projected by the builders and in the scientific literature, the following operational data from Qinghai Supcon Delogha 50MW CSP station is discussed.


This station is one of the first China national CSP demonstration projects located in Delingha City, Qinghai Province. The main data of the project are following:


15.png


This project was connected to the grid on December 30, 2018. After the commissioning period, it entered the assessment period on July 26, 2019. From July 26, 2019 to July 25, 2020, the power station completed its first full annual normal operation cycle. During this period, the cumulative DNI was 2013 kWh/m2 (slightly worse than the typical weather year DNI 2043 kWh/m2). According to the performance model, the expected generation should be 1374.8 GWh, while the actual power generation was 1218 GWh, with the achievement rate of 88.6% during the testing phase. This number is expected to increase with normal operation and with gaining experience with the power plant operation. There were also non-technical reasons slightly impacting the overall power generation, such as power grid maintenance, test daily 11 am -3 pm to reduce the load operation mode, etc. Figure 1 shows expected and real power generation of the plant by month.


11.png

As shown in the Figure 2 from February 1 to February 13, 2020, we verified the operation mode of full load during the day, load reduction at night, and continuous 24h non-stop operation, achieving three records simultaneously:

• 293 hours of continuous, uninterrupted operation, 

• the cumulative power generation of continuous operation was 8.39 GWh, 

• and the average achieved rate of power generation during continuous operation was 105.2%, which fully demonstrates the advantages of CSP in providing a continuous and stable power output also during the night.


119.png


Finally, let’s not forget that the technology evolves with time and, especially CSP technology improves with more power plants being constructed. We should not be misguided about the performance of the technology only because of some problems that happened in a power plant seven years ago, when there was almost no experience with the solar tower design and operation.


We will continue writing and providing new data about other so called “drawbacks” of CSP stations in next articles. Follow us on the social media to not miss it!


Written by Alina Gilmanova,Haobin Zhang



Leave your thoughts here

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-176 2178 1814

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news