China 4 CSP demos quit and 16 totaling 1014MW to be completed successively by 2020
2018.08.15 From: CSP Focus光略咨询
On May 22, China National Energy Administration (NEA) issued a notice on “Promoting the Construction of 1st Batch of Concentrated Solar Power Demonstration Projects”. The notice pointed out that the deadline for the first batch of CSP demo projects could be extended to 2020, but with an electricity price reduction mechanism.
It is an important measure to promote the progress of CSP technologies and the development of the industry.
To read the detailed sum-up of China 1st batch CSP demos:
Free Report: Progress of China 1st batch CSP demonstrations and suggestions to follow-up projects development
As CSP Focus keeps reporting, the government clearly stated that only those which could be completed and put into production by December 31, 2018, would adopt the benchmark on-grid price of RMB 1.15 per kilowatt-hour (inclusive of taxes).
However, according to the actual conditions of the 1st batch of 20 demonstration projects, the construction deadline can be extended to December 30, 2020, meanwhile, an electricity price reduction mechanism for overdue projects will be established.
The notice also stated that those who had failed to submit construction commitments on time (by the end of February, 2018) would no longer enjoy the policies for demonstration projects, as a result, there are now 16 of the original 20 demo projects remaining on the list, with the total capacity of 1014MW.
As Mr. Sun Rui, Deputy Dean of China Electric Power Planning & Engineering Institute interpreted in CSP Focus China 2018 conference this late March, 4 projects totally 335MW quit, and other 16 are expected to enjoy different levels of FiT.
5 projects totaling 300MW will be completed on time and enjoy the original FiT of RMB 1.15/kWh.
3 projects totaling 150MW will be finished half year late by June 30, 2019, and enjoy the FiT of RMB 1.14/kWh.
6 projects totaling 364MW will be finished one year late by December 31, 2019, and enjoy the FiT of RMB 1.12/kWh.
2 projects totaling 364MW will be finished two year late by December 31, 2020, and enjoy the FiT of RMB 1.07/kWh.
As a result, 7 of 16 take parabolic trough technology (2 thermal oil, 2 molten salt), and 7 molten salt power tower, 2 Fresnel (1 water, 1 molten salt).
The detailed list is as below:
The final decision will be confirmed by the government soon.
As CSP Focus gets from the industry resources, 9 out of the 16 demos are in actual construction, and 7 are in early-stage of preparation.
To read the full list of the confirmed vendors and candidate suppliers for China under-going CSP projects, please click:
Free Report: Suppliers List of China Key CSP Projects
More China CSP information please visit www.cspfocus.cn/en, and you are also welcome to join the upcoming CSP Focus Innovation 2018(Oct.25-26, China).
More from CSP Focus
NextRefractaris leads the construction of solar shields for concentrated solar power
World largest Fresnel CSP project operates in Dunhuang China
Middle East and North Africa’s Concentrated Solar Power Knowledge and Innovation Program
ContourGlobal sells 49% stake of Spainish CSP assets for EUR 134M
Chile Largest CSP Project in Pictures: Cerro Dominador 110MW molten salt tower project
Molten salt bidding of China Yumen Xinneng solar CSP project opened
247SOLAR CEO BRUCE ANDERSON TO INTRODUCE NEXT GENERATION LOW-COST CSP
Concentrated solar power accounted for 3.5% of electricity in August in Spain
Leave your thoughts here
Reports(Member Only)
See more+-
CSP Focus Membership Proposals
We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea
-
The Latest CSP Focus Monthly Update
Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.
-
CSP Project Monthly Update 2022 December Edition
CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.
-
Presentations-CSP Focus China 2021
The Report is for CSP Focus Members only.
Upcoming Events
See more+-
12th CSP Focus China 2022
2022.04.21-22 Beijing
-
11th CSP Focus China 2021
2021.10.28-29 Beijing
-
10th CSP Focus China 2020
2020.10.22-23 Beijing, China
Project Updates
See more+-
Lanzhou Dacheng Dunhuang CSP Project
Asia Pacific-China,Operational,Parabolic Trough
-
Luneng Haixi 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower
-
Dubai 950MW NOOR Energy 1 CSP+PV Project
MENA-UAE,Under construction,Power Tower
-
Power China Gonghe 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower