Sandstone CSP to offer storage below $90/MWh to California utilities
2018.09.05 From: newenergyupdate
Boosted by streamlined permitting and falling costs, Sandstone project developer SolarReserve is preparing to enter into power purchase talks with Californian utilities in the coming months, Kevin Smith, CEO of SolarReserve, told New Energy Update.
SolarReserve's Sandstone CSP project in the Nevada desert targets California's peak power needs. (Image credit: MBBirdy.)
California’s SolarReserve is among a group of solar developers hoping to benefit from recent streamlining of permitting processes for U.S. federal lands.
SolarReserve's giant Sandstone CSP project would see up to 10 towers built in the Nevada desert, providing some 2 GW of renewable energy capacity across daytime and nighttime periods. The plant will feature 10 hours of molten salt storage capacity and much of the power would be dispatched to California to cover high afternoon and evening power demand which cannot be met by PV and wind capacity.
The proposed site for Sandstone is up to 20,000 acres of federal land around 225 miles northwest of Las Vegas, Nevada, managed by the Bureau of Land Management (BLM). Sandstone is one of eight large solar projects in the US. south west--the others are PV—which are following a streamlined BLM land approval process.
SolarReserve is currently conducting baseline site studies towards the Sandstone permit application and the full review process is set to start in the spring of 2019, Gregory Helseth, Renewable Energy Manager, Nevada at the Bureau of Land Management (BLM), told New Energy Update.
The new approval process requires the regulatory decision to be made within a year, "so you’re looking at a full decision by spring 2020,” Halseth said.
SolarReserve must also secure long-term power purchase agreements (PPAs) to back the project financing. Competition over PPA procurement is growing as the cost of wind and solar power continues to plummet.
The energy storage capacity of the Sandstone plant will help SolarReserve secure contracts with California utilities seeking to hit the state’s mandated clean energy targets, Kevin Smith, CEO of SolarReserve, told New Energy Update.
Sandstone’s towers would each provide 10 hours of full load storage, equivalent to 20,000 MWh per tower of dispatchable renewable power available across the critical peak evening demand period.
“California utilities will value Sandstone’s huge amount of energy storage…Our target pricing is to be well under 9 cents/kw-hour ($90/MWh),” Smith said.
SolarReserve will start discussions with utilities later this year, he said.
California hourly system energy prices in 2017
Source: California ISO
Key project
The construction of the Sandstone project would reignite U.S. CSP construction and bridge a dearth of activity in the coming years.
The U.S. currently hosts 1.8 GW of operational CSP capacity but new project activity has dwindled in recent years as PV and wind costs have plummeted. Seven U.S. CSP projects have been cancelled, 15 are on hold and the 850MWth Belridge oilfield solar thermal project in California is the only project currently in the planning phase, according to the New Energy Update CSP Tracker.
US large-scale CSP plants
Source: CSP Today Global Tracker
U.S. CSP projects have faced opposition from environmental groups and SolarReserve expects a "rigorous and proper environmental review", Smith said.
"We recognize that this is a very large and complex project and we are not looking to rush it through the process,” he said.
The selected site for the Sandstone project is adjacent to SolarReserve’s operational 110 MW Crescent Dunes CSP plant, which has a proven low environmental impact, Smith noted.
"So we don’t expect any issues," he said.
If SolarReserve secures permits and PPA contracts for Sandstone, construction of the first two or three towers could start by the end of 2020 or early 2021, Smith said.
"The plan is to build Sandstone in phases over 6 to 7 years, with 2 to 3 towers initially,” he said.
Going forward, CSP developers predict growing intermittent PV and wind capacity will open up new opportunities for CSP with storage. Developers also expect high-temperature next-generation designs will significantly improve the competitiveness of CSP plants, although these designs are several years from commercial deployment.
Falling costs
The Sandstone plant design is similar to SolarReserve's Crescent Dunes plant, which entered into operation in late 2015.
The Crescent Dunes project secured a 25-year purchase contract with NV Energy at $135/MWh. Global CSP costs have fallen significantly since then, driven by technological advancements and installation learnings. Since Crescent Dunes, SolarReserve has been actively developing projects in Chile, South Africa and Australia.
Sandstone will clearly benefit from economies of scale and series and the predicted capital cost of the heliostat field is 50% lower than on Crescent Dunes on a $/MWh basis, Smith noted.
Improvements in the molten salt receiver for Sandstone include higher thermal capacity (765 MWth), improved tube materials and coating efficiency for optimal solar energy collection, and new methods for solar flux measurement to increase efficiency, he said.
In a tender in Chile in 2016, SolarReserve bid its 240 MW Copiapo project with 14 hours of storage at a record-low CSP price of $63/MWh. Costs differ significantly between markets however and the power price for Sandstone will not be as low as in Chile, Smith said. Chile enjoys higher solar direct normal irradiance (DNI) levels and local salt reserves and supply chain efficiencies contributed to SolarReserve’s record-low bid.
While battery costs continue to fall and lower the cost of PV or wind plus storage, Smith is confident the Sandstone plant will remain competitive in the coming years.
“Battery technology will be quite a bit more expensive than our price, so we believe we’re well positioned in the California market,” he said.
Relevant CSP Conference: CSP Focus Innovation 2018(Oct.25-26, Xi'an, China.)
More from CSP Focus
NextCentrifugal Concentrated Solar Power could offer siting breakthroughs, $60/MWh power
Eltherm South Africa Lands Kathu Concentrated Solar Power Plant Heat Tracing Contract
Opinion- The Advantages to Develop CSP with Storage in China
Fraunhofer ISE Develops Solutions for Optimized Water Use in Solar Thermal Power Plants
Molten salt bidding of China Yumen Xinneng solar CSP project opened
Climate Tracking: Morocco Makes ‘Impressive Progress’ in Limiting Global Warming
Financing is key to China's ambitious Concentrated Solar Power goals
Leave your thoughts here
Reports(Member Only)
See more+-
CSP Focus Membership Proposals
We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea
-
The Latest CSP Focus Monthly Update
Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.
-
CSP Project Monthly Update 2022 December Edition
CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.
-
Presentations-CSP Focus China 2021
The Report is for CSP Focus Members only.
Upcoming Events
See more+-
12th CSP Focus China 2022
2022.04.21-22 Beijing
-
11th CSP Focus China 2021
2021.10.28-29 Beijing
-
10th CSP Focus China 2020
2020.10.22-23 Beijing, China
Project Updates
See more+-
Lanzhou Dacheng Dunhuang CSP Project
Asia Pacific-China,Operational,Parabolic Trough
-
Luneng Haixi 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower
-
Dubai 950MW NOOR Energy 1 CSP+PV Project
MENA-UAE,Under construction,Power Tower
-
Power China Gonghe 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Operational,Power Tower