SHANGHAI - January 2020 -- Significant progress has been made in the Dubai 700 MW concentrated solar power project, announced as the world’s largest single-site CSP project. On Jan 9th, a topping-out ceremony for the project’s 222-meter central tower was held, welcoming representatives from Shanghai Electric - the project’s general contractor - Dubai Electricity and Water Authority (DEWA), Noor Energy 1 and China Construction Third Engineering Bureau.


“SEGC(Shanghai Electric Group Company) showed us their outstanding performance, finishing the concrete solar tower according to schedule, even if they suffered tough challenges along the way,” said Enrique Valades Nieto, Noor Energy 1 Construction Manager.



The 700 MW CSP project marks phase four of the Mohammed bin Rashid Al Maktoum Solar Park in Dubai and is a crucial part of the UAE government’s “Vision 2021” initiative to ensure sustainable and environmentally friendly development.


In addition to “Vision 2021”, the government also launched the “Energy Strategy 2050 Plan”, which aims to increase the contribution of clean energy in the total energy mix from 25 per cent to 50 per cent by 2050. Once operational, the CSP plant will reduce Dubai’s carbon footprint by 1.6 million tons per year.


Sustainability is the focus of the project. Shanghai Electric engaged experts and partners to relocate wild animals and 180 mesquite trees across the 40 sq km site to a new wildlife park to minimize the impact of construction.


The project also aims to generate jobs for residents and is supported by an international team. It is estimated that as the project progresses, it will create around 6000 jobs in the technology, energy management and construction sectors.


About Concentrated Solar Power Systems


Concentrated solar power systems generate solar power by using mirrors or lenses to concentrate a large area of sunlight onto a small area. Electricity is generated when the focused light is converted into heat, which drives a steam turbine connected to an electrical power generator. The solar power collectors of the 700 MW CSP plant include both tower and tube collectors. The central tower is the crucial component of the plant and is used for receiving all the focused sunlight from the 70,000 mirrors to increase the temperature to more than 500 ºC, and with this heat produce the steam turbine connected to the electrical power generator. With a total height of 267 meters, it is currently the world’s highest thermal tower.


About Shanghai Electric


Shanghai Electric Group Company Limited (SEHK:2727, SSE:601727) is principally engaged in design, manufacture and distribution of electric power and industrial equipment. Its primary focus is on new energy, including the manufacture and sale of wind turbines and components and nuclear power equipment; efficient and clean energy business, including the manufacture and sale of thermal power equipment and power transmission and distribution equipment; industrial equipment, including the production and sale of elevators and motors; modern service industry, including the contracting of construction projects of thermal power and transmission and distribution projects, as well as other businesses.




Upcoming CSP events:


10th CSP Focus China 2020 (March.25-26, Beijing China) 

5th CSP Focus MENA 2020(June.23-24,Dubai, UAE)


More CSP news and reports please visit www.cspfocus.cn 

or CSP Focus social media on LinkedInTwitterFacebook.



Leave your thoughts here

Latest News

See more+
  • What we've known about Indian CSP tender in Q1 2024

    It was reported that India will carry out a round of renewable energy bidding in the first quarter of 2024, which requires bidders to submit a program must contain more than 50% of the CSP capacity. This news got great attention in the past weeks on the possibility of CSP revival in India. But how about the challenges to hinder the development of Indias solar thermal power generation in the past y

  • CSP Project Tenders Last Week (Apr.15-21)

    Procurement and Construction Bidding- Xinhua Hydropower Bozhou 100MW CSP ProjectOn April 17, Xinhua Botai (Bole) Power Investment Co., Ltd. issued a bidding announcement for Xinhua Hydropower Bozhou 100MW CSP+900MW PV Project bid section VII: 100 MW CSP project PC general contracting. Bidding document acquisition time: from April 17, 2023 to April 24, 2023 at 16:00.One step closer towards Australi

  • One step closer towards Australia’s first commercial scale concentrated solar power plant

    On behalf of the Australian Government, the Australian Renewable Energy Agency (ARENA) has announced it has approved $65 million in funding to Vast Solar to construct VS1, a first-of-a-kind 30 MW / 288 MWh concentrated solar power (CSP) plant in Port Augusta, South Australia.ARENA’s funding for VS1 is conditional upon the project reaching financial close, which is targeted to occur in late 2023.

  • CSP Project Tenders Last Week (Apr.8-14)

    EPC Tender- SPIC Shanshan 100MW CSP ProjectOn April 8, SPIC Henan Company issued a public bidding announcement for the EPC general contract of SPIC Shanshan 100MW CSP Project. Application deadline: April 14, 2023, 23:59.Olympic Brewery: Paving the way for beer production by harnessing solar energy, in partnership with AbsoliconAthens, March 4, 2023 - In the framework of its ESG strategy with the k

Reports(Member Only)

See more+
  • CSP Focus Membership Proposals

    We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea

  • The Latest CSP Focus Monthly Update

    Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.

  • CSP Project Monthly Update 2022 December Edition

    CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.

  • Presentations-CSP Focus China 2021

    The Report is for CSP Focus Members only.

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news