Detailed Progress on China 1st phase 20 CSP pilot projects

2017.01.24     From: CSP Focus

It has been over 4 months since the official announcement of China 1st phase 20 CSP pilot project list in September 2016. As the government said only those which could be completed by the end of 2018 would enjoy the FiT of RMB1.15/kWh. Thus, around only 23 months are left for construction, which seems to be quite hard work for the project participators. Below are the newly updated progresses of the 20 pilot CSP projects: 

Freereport: List of China 1st Phase 20 CSP Pilot Projects


1.Under construction/bidding

1.1 CGN Delingha 50MW Parabolic Trough Project

Feasibility study institute: Northwest Electric Power Design Institute

Recent news: providers of detailed design, receiver tube, reflector, steam turbine and other key components have been confirmed. Project construction keeps going on even in winter.

1.2 Beijing Shouhang IHW Resources Saving Technology (SunCan) 100MW Molten Salt Tower Project

Feasibility study institute: Guangdong Northeast Electric Power Design Institute

Recent news: 1st phase of 10MW tower project has been put into operation. 2nd phase of 100MW project is under construction with the tower foundation established. The steam turbine tender has been completed, and some providers of other key components have been confirmed. It is expected to be completed in the mid of 2018.

1.3 Shenzhen Jinfan Akesai 50MW molten salt Parabolic Trough Project

Feasibility study institute: Northwest Electric Power Design Institute

Recent news: Electricity matching started in 2013, and water diversion project in 2015. Supporting facilities are under construction, and equipment procurement is in the preparation stage.

1.4 Qinghai SUPCON Solar Delingha50MW Molten Salt Tower Project

Feasibility study institute: Northwest Electric Power Design Institute

Recent news: 1st phase of 10MW tower project has been put into operation. Feasibility study is completed and commencement ceremony has been held. Key components like steam turbine is under procurement.

1.5Rayspower Group Yumen 50MW Parabolic Trough Project

Feasibility study institute: Northwest Electric Power Design Institute

Recent news: feasibility study is completed and commencement ceremony has been held. Inner Mongolia Electric Power Survey Design Co., Ltd has been awarded to be responsible for preliminarily design, survey and general design.

1.6 Northwest Electric Power Design Institute Hami 50MW MS Tower Project

Feasibility study institute: Northwest Electric Power Design Institute

Recent news: feasibility study is completed and commencement ceremony has been held. Biddings for solar field system, steam turbine, SGS, and generator have been launched and the results will come out soon. 

1.7 Zhongyang Chabei 64MW Parabolic Trough Project

Feasibility research Institute: Central South Survey Design Institute

Recent news: The commencement ceremony was held in 2014. The developer is working on financing. 

1.8 Yumen Xinneng 50MW Molten Salt Tower Project

Feasibility study institute: North China Power Engineering Co., Ltd 

Recent news: feasibility study is being reviewed and EPC tender is going on.

1.9 Guohua Yumen 100MW Molten Salt Tower Project

Feasibility study institute: Northwest Electric Power Design Institute

Recent news: feasibility study is completed and EPC tender is going on. The winner will be awarded on Feb.8 out of 6 candidates. 

1.10 China Nuclear Royal Tech Wuzhongqi 100MW Parabolic Trough Project

Feasibility study institute: North China Power Engineering Co., Ltd 

Recent news: feasibility study is completed and the key component biddings are expected to be open soon. Project construction is expected to start in mid of April.

1.11 Royal Tech Yumendongzhen 50MW Parabolic Trough Project

Feasibility study institute: Northwest Electric Power Design Institute

Recent news: feasibility review has been finished and key component biddings are expected to be open soon. Project construction is expected to start in mid of April.


2.In preparation stage

2.1 Huanghe Hydropower Development 135MW Molten Salt Tower Project

Feasibility study institute: Northwest Electric Power Design Institute

Recent news: feasibility study has been finished, and technical route has been changed to molten salt tower.

2.2 Zhangbei Huaqiang Group Zhangjiakou DSG 50MW CLFR Project

Feasibility study Institute: Hebei Institute of Survey and Design

Recent news: 1st phase of 10MW is expected to operate soon, and feasibility study for the 50 MW project has been completed.

2.3 DCTC Dunhuang 50MW Molten Salt CLFR Project

Feasibility study institute: Northwest Electric Power Design Institute

Recent news: The feasibility review has been finished.

2.4 Northern United Power Urad 50MW CLFR Project

Feasibility study institute: North China Power Engineering Co., Ltd 

Recent news: The feasibility study has been finished.

2.5 Dahua Inc. Shangyi 50MW Molten Salt Tower Project

Feasibility study institute: Northwest Electric Power Design Institute

Recent news: feasibility study review has been started, and technical route has been changed to molten salt tower.

2.6 Northwest Survey&Design Gonghe 50MW Molten Salt Tower Project

Feasibility study Institute: Northwest Institute of Survey and Design

Recent news: feasibility study review work started in late Nov. and preliminary design is under preparation. 

2.7 CITIC Zhangbei DSG 50MW CLFR Project

Feasibility study Institute: Hebei Institute of Survey and Design

Recent news: carrying forward

2.8 CECIC Gansu Wuwei 100MW Parabolic Trough Project

Feasibility study institute: North China Power Engineering Co., Ltd 

Recent news: carrying forward

2.9 China Three Gorges New Energy Jinta 100MW Molten Salt Tower Project

Feasibility study institute: North China Power Engineering Co., Ltd 

Recent news: carrying forward 


Leave your thoughts here

Latest News

See more+
  • Magtel launches a hybrid solar power plant that will produce energy at night in Hornachuelos

    The Cordoba-based engineering company Magtel has started the environmental consultation phase of the first hybrid renewable power plant to be proposed in the province of Cordoba. It will have (if it gets the papers) the two available solar technologies, solar thermal and photovoltaic, but it will have a peculiarity. You can create electrical energy at will. When the energy network demands it. Even

  • CSP Project Tenders Last Week (Sept 1-11)

    Equipment Procurement Tenders- CGN New Energy Jilin 100MW CSP ProjectOn September 2, Daan Guangtou Zhongneng CSP Company issued a bidding announcement for the turbine generator set, steam generation system, solar concentration and heat collection system, cold salt pump, hot salt pump and thermoregulation pump of CGN New Energy Jilin 100MW CSP Project.Tender for Turbine Systems-Tibet Mining Zabuye

  • Letlhakane Concentrated Solar Power Plant in Botswana

    The Letlhakane Concentrated Solar Power Plant is a planned 100 MWconcentrated solar power station in Botswana. The owner, developer and operator of this solar power complex will be an independent power producer, whose identity will be revealed when the ongoing open bidding is concluded. Bids were received until June 2022.The power generated here is expected to be bought by Botswana Power Corporati

  • DEWA receives four bids from international companies for sixth phase of solar park

    Dubai Electricity and Water Authority (DEWA) has received 4 bids from international companies for consultancy contract for the sixth phase of the Mohammed bin Rashid Al Maktoum Solar Park, Dubai Media Office (DMO) announced on Tuesday.The single-site solar park is the largest of its kind in the world, using the Independent Power Producer (IPP) model, with a production capacity of 5,000 megawatts b

Reports(Member Only)

See more+

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news