Luneng Haixi 50MW Molten Salt Tower CSP Project

2022.08.05     From: CSP Focus光略咨询

   2022-7


Project Schedule

 ● 2016-12-26, Project approval from National Energy Administration

 ● 2017-6-30, Project construction started

 ● 2018-3-20, Construction of Receiver Tower Foundation Started

 ● 2018-10, COD of PV and Wind projects

 ● 2018-11-21, Construction completion of receiver tower (147.4m of 181.1m)

 ● 2019-1-2, Civil work completed, equipment installation started

 ● 2019-2-28, Installation of Receiver Supporting Sturcture Started

 ● 2019-4-30, 2,100 heliostats installed (4,400 in total)

 ● 2019-6-6, Installation of Receiver Supporting Sturcture Completed

 ● 2019-7-4, Steam turbine and generator installed

 ● 2019-8-15, Salt Melting Started

 ● 2019-9-5, Grid connection acceptance

 ● 2019-9-19, Grid Connected Successfully

 ● 2020-8-27, 120 Hour Reliability Operation Passed


Full report (Member Only)


Project Overview


With total capacity of 700MW, Luneng Haixi Geermu Multi-energy Complement Integration Optimization Pilot Project consists of 200MW PV, 400MW Wind, 50MW CSP and 50MW energy storage system. 


The annual electricity generation is expected to be around 1262.5GWh after completion of the project, reducing standard coal consumption of 401,500 metric ton and dust emission of 5431.96 metric ton. The CSP plant is normally named Luneng Haixi 50MW Molten Salt Tower CSP Project, consisting of one 188m receiver tower, 4,400 heliostats, 12h thermal electricity storage system. 


The CSP project is expected to be operational before August 30th, 2019.


Apply CSP Focus Membership to see full report


Project Participants

   

Apply CSP Focus Membership to see full report

                                                                                                                                                              

 Plant photos






Leave your thoughts here

Latest News

See more+
  • Dubai’s concentrated solar power project starts supplying electricity to the grid

    On November 29 (Dubai Time), the Trough Unit No. 1 facility of Shanghai Electric’s 700MW solar thermal and 250MW photovoltaic solar power plant in Dubai has successfully achieved grid-connected electricity generation, marking a significant milestone along the path of the firm’s entry into the renewable energy sector. The facility is already delivering top-notch technical parameters and reliable

  • Four bidders shortlisted for 200MW solar plant

    The plant, which will use lenses or mirrors to focus a large area of sunlight onto a receiver, is due to be operational by 2027 and is the flagship renewable project in government’s Integrated Resources Plan (IRP) for energy development in the years to 2040.On Tuesday, the Ministry of Minerals and Energy published a shortlist of four bidders who include major global players with thousands of mega

  • CSP Project Tenders Last Week (Nov.14-20)

    Project Construction Supervision Bidding- POWERCHINA Ruoqiang 100MW CSP + 900MW PV ProjectOn Nov. 14, POWERCHINA Renewable Energy Co., Ltd issued a tender announcement for the construction supervision of the POWERCHINA Ruoqiang 100MW CSP + 900MW PV Project. According to the announcement, the owner of POWERCHINA Ruoqiang 100MW CSP + 900MW PV Project is POWERCHINA Ruoqiang Ruida Energy Development C

  • CSP Project Tenders Last Two Week (Nov. 1-13)

    Vacuum Pump Tender- Akesai Huidong New Energy CSP + PV Pilot ProjectOn November 7, East China Electric Power Design Institute Co., Ltd. of China Power Engineering Consulting Group issued a procurement announcement for vacuum pumps for the Akesai Huidong New Energy CSP + PV Pilot Project.Latest Milestone- Akesai Huidong New Energy CSP + PV Pilot ProjectAccording to the Aksai County Government, the

Reports(Member Only)

See more+

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news