Yumen Xinneng 50MW molten salt tower CSP plant
2020.01.14 From: CSP Focus 光略咨询
2020-1-14
Project Schedule |
● Before the middle of 2020 (expected), Modules No.1-3 connected to the grid ● July, 2019, Module No.1 tested and molten salt was heated to 570℃; Heliostats of Module No.2 almost installed; Modules No.3-10 under construction ● March, 2019, steam turbine & steam generation equipment installed ● Aug.5th, 2018, main transformer installed ● April, 2018, foundation of steam turbine started construction; Modules No.2-5 started construction ● March, 2018, overall installation of Module No.1 completed ● Dec.7, 2017, molten salt TES started constructio ●Dec. 4, 2017, heat exchanger bidders announced & steam generator bidding restarted. ● September, 2017, designing plan reviewed ● Jun.8, 2017, officially broke ground ● Dec.16, 2016, feasibility study meeting held |
Project Overview |
Yumen Xinneng 50MW molten salt tower CSP plant was officially selected as one of China 1st batch of CSP pilot projects in September 2016. With total investment of RMB 1.78 billion, the project is expected to be completed in 2 years. The project is located in Zhengjiashawo CSP Park, 15km far from new downtown of Yumen city, Gansu Province. The 50MW project takes beam-down CSP technology with 15 mirror field modules, and one 9-hour molten salt thermal storage system & steam turbine set. The annual generating capacity is under load of 4328 hours.
The project broke ground in June 2017, and 3 of the 15 modules are expected to be connected to the gird by the end of September, 2019. It will be the first large-scale commercial CSP plant in the world taking innovative beam-down molten salt tower CSP technology.
As recognized by CSP industry players, the Direct Normal Irradiance (DNI) should be above 1,700kW.h/㎡, and the DNI in Yumen is around 1,901 kW.h/㎡, indicating that Yumen is rich in solar resources and a great place for building CSP plants.
Apply CSP Focus Membership to see full report
Project Participants |
Apply CSP Focus Membership to see full report
Plant photos |
More from CSP Focus
NextLeave your thoughts here
Latest News
See more+-
HERLOGAS Ends SUCCESSFULLY the WORLD'S LARGEST Salt Melting In DUBAI, DEWA CSP - Noor Energy 1 Project in Set 3-4 of PT1.
In this project HERLOGAS collaborates with Shanghai Electric with the melting process of 560,000 tons of salt and the preheating of the 26 storage tanks, to date HERLOGAS has successfully melted 115,000 tons of salt successfully and preheated 4 salt tanks, This melting process that we have ends SUCCESSFULLY in PT1 Set 3-4.Noor Energy 1 PSC will be implementing the 4th phase of Mohammed bin Rashid
-
ACCIONA Energía celebrates 15-year anniversary of the Nevada Solar One Concentrated Solar Plant
June 30, 2022. ACCIONA Energía, world leader in renewable energy, celebrates 15 years of operations for its Nevada SolarOne Concentrated Solar Plant (CSP) located in Boulder City, Nevada. The plant generates up to 64 MW per hour, enough to power 12,500 Nevada households on an annual basis, and it removes an estimated92,000 metric tons of CO2 emissions annually. ACCIONA Energía’s Nev
-
Why is nobody talking about concentrated solar power?
Concentrated solar power has a lot more potential than traditional solar panelsDarmau Lee, UnsplashWhen most of us think about solar power, we picture large black panels made of silicon, unattractively stuck on top of houses. These photovoltaic (PV) solar cells are set to play a key role in the global push to “Net Zero”, and you could be forgiven for thinking that, alongside some wind farms here
-
EPC and Project Supervisor Tendering - Guazhou 700MW CSP+PV+Wind
June 2022Three Gorges Hengji Nengmai Guazhou 700MW CSP+PV+Wind Project was part of the 1.3GW CSP projects released last year in China. The project feasibility study was reviewed and approved in Feb 2022. The project developer issued the tender of EPC by the end of April and tender Project Supervisor 5th of May.Project HighlightsThe Project is consisting of 200MW PV, 400MW Wind and 100MW CSP, and t
Reports(Member Only)
See more+-
Presentations-CSP Focus China 2021
The Report is for CSP Focus Members only.
-
Presentations-CSP Focus China 2020
The Report is for CSP Focus Members only
-
CSP Performance and Future Auctions in Spain
This Report is for CSP Focus Members only. Click "Apply" to join as CSP Focus Member.
-
Hybrid with other REs – Win Win Strategy of CSP
This Report is for CSP Focus Members only. Click "Apply" to join as CSP Focus Member.
Upcoming Events
See more+-
12th CSP Focus China 2022
2022.04.21-22 Beijing
-
11th CSP Focus China 2021
2021.10.28-29 Beijing
-
10th CSP Focus China 2020
2020.10.22-23 Beijing, China
Project Updates
See more+-
Luneng Haixi 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Under construction,Power Tower
-
Dubai 950MW NOOR Energy 1 CSP+PV Project
MENA-UAE,Under construction,Power Tower
-
Power China Gonghe 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Under construction,Power Tower
-
Supcon Delingha 50MW Molten Salt Tower CSP Project
Asia Pacific-China,Under construction,Power Tower