Yumen Xinneng 50MW molten salt tower CSP plant

2020.01.14     From: CSP Focus 光略咨询

2020-1-14


Project Schedule

  


● Before the middle of 2020 (expected), Modules No.1-3 connected to the grid

● July, 2019, Module No.1 tested and molten salt was heated to 570℃; Heliostats of Module No.2 almost installed; Modules No.3-10 under construction

● March, 2019, steam turbine & steam generation equipment installed

● Aug.5th, 2018, main transformer installed

● April, 2018, foundation of steam turbine started construction; Modules No.2-5 started construction 

● March, 2018, overall installation of Module No.1 completed

● Dec.7, 2017, molten salt TES started constructio 

Dec. 4, 2017, heat exchanger bidders announced & steam generator bidding restarted.  

● September, 2017, designing plan reviewed

● Jun.8, 2017, officially broke ground

● Dec.16, 2016, feasibility study meeting held


     Full report view online


Project Overview


Yumen Xinneng 50MW molten salt tower CSP plant was officially selected as one of China 1st batch of CSP pilot projects in September 2016. With total investment of RMB 1.78 billion, the project is expected to be completed in 2 years. The project is located in Zhengjiashawo CSP Park, 15km far from new downtown of Yumen city, Gansu Province. The 50MW project takes beam-down CSP technology with 15 mirror field modules, and one 9-hour molten salt thermal storage system & steam turbine set. The annual generating capacity is under load of 4328 hours. 


The project broke ground in June 2017, and 3 of the 15 modules are expected to be connected to the gird by the end of September, 2019. It will be the first large-scale commercial CSP plant in the world taking innovative beam-down molten salt tower CSP technology. 


As recognized by CSP industry players, the Direct Normal Irradiance (DNI) should be above 1,700kW.h/㎡, and the DNI in Yumen is around 1,901 kW.h/㎡, indicating that Yumen is rich in solar resources and a great place for building CSP plants.

     

Basic information

Location

Zhengjiashawo CSP Park

Capacity

50MW

Investment

1.78 billion

Annual generating capacity

4328h

Thermal energy stroage hours

9h


Project Participants


Tendering Item

Bidding Winner

Turnkey EPC

CSEEC-China Sinogy  Electric Engineering Co.,Ltd.

Subcontractor of Energy Collecting  and Storage System (Equipments such as Heliostats, Beam-down Tower, Central  Receiver, Molten Salt Tank…and construction)

Jiangsu Xinchen CSP

Turnkey EPC of Central Storage  Tank

China Chengda  Engineering Co., Ltd.

Thermal Insulation for TES  Tank/Heat Receiver/Pipeline

LUYANG ENERGY-SAVING  MATERIALS CO.,LTD.

Molten Salt Vertical Pump

Ruhrpumpen

Electric Heat Tracing

MICC

Steam Turbine

Shanghai Turbine  Works Co., Ltd.

Electric Generator

JPEF-SHANDONG JINAN  POWER EQUIPMENT FACTORY

Low Voltage Cabinet

Schneider Electric

Steam Generator

Dongfang Boiler  Group Co., Ltd

Air Cooling/Dry Cooling System

SEC - SPX  Engineering Technology Co., Ltd.

Molten Salt Storage Tank Heater

Zoppas Industries

Stainless Material for TES Tank  Manufacture

Taiyuan  Iron&Steel (Group) Co.,Ltd

Ultrasonic Flowmeter

Flexim

Molten Salt Ultrasonic Flowmeter

Krohne

Fastener

EPRESS SYSTEMS  (SHENZHEN) LTD

300t Molten Salt-Sodium Nitrate

Hualong Ammonium  Nitrate Co.,Ltd Shandong Ocean Chemical

Power Block Construction &  Installation

JEPC3-China Energy  Engineering Group Jiangsu No.3 Electric Power Construction Co., Ltd.

                                                                                          

 Plant photos


More from CSP Focus

Next

Leave your thoughts here

Latest News

See more+
  • Innovation shaping the future of solar power

    Today, the most common method of harvesting solar energy is photovoltaic solar (PV), which uses solar cells to convert sunlight directly into electrical power. A CSP tower on the other hand, uses mirrors and lenses to concentrate sunlight towards a solar receiver, which is then used to generate and store high-temperature heat through a heat transfer fluid. This heat can then be used immediately ei

  • Spain Confrims 200MW CSP Auction in April 2022

    In the initial 2 renewable energy auction rounds under REER, Spain has so far awarded 2.902 GW of solar PV and 3.256 GW of wind energy capacity. On April 6, 2022, it plans to hold the 3rd auction to award 500 MW capacity. The Spanish Ministry for the Ecological Transition and the Demographic Challenge (MITECO) has announced April 6, 2022 as the day when it plans to hold the country’s 3rd renewabl

  • 1.3GW CSP Projects Planned to Start in 2022

    A new wave of CSP development, and GW of CSP projects, will emerge in China and the rest of world after the staggering year of 2021. As was declared clearly in “Action Plan for Carbon Dioxide Peaking Before 2030”, an official statement released by the State Council of China, “…to promote CSP development actively, and establish Renewable Energy Composite Complex integrating CSP, PV and Wind…”

  • Rediscovering Concentrated Solar Power: story from China

    Start of new series of articles with new data on CSP power plant. Recentlysome media, such as Energyskeptic, falsely accused CSP technology of being unreliable, full of glitches and having a low energy return. Theiropinion refers to certain early development faults of the technology, mainly based on the US experience, where new CSP stations have not been built since 2015. Indeed, all power product

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-176 2178 1814

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news