Shouhang Dunhuang 100MW Molten Salt Tower CSP Project

2022.08.03     From: CSP Focus 光略咨询

   2022-7


 Project Schedule


  • 2014, Project design began

  • 2015-11-9, Ground Breaking Ceremony

  • 2016-11, Field leveling work started, core component procurement and main work construction began

  • 2017-5-13, Structural construction of administration building finished

  • 2017-11-4, Tower completed

  • 2018-2, 1000 heliostats installed

  • 2018-5, Civil work completed

  • 2018-10, Project installation completed

  • 2018-11, Under commissioning

  • 2018-12-28, Connect to grid

  • 2019-3-13, PPA Signed with Local Grid Company


 Full report (Member Only)


 Project Overview


Shouhang Dunhuang 100MW Molten Salt Tower CSP Plant(hereinafter referred to as “the project”) is one of the 1st batch of 20 pilot CSP projects in China and being developed with a steady progress. Belonging to the second phase of Shouhang’s Dunhuang CSP plan (Phase one 10MW completed), the project is the largest molten salt tower CSP plant during construction period in China and its equipped solar field will be the largest one in the world when it’s completed.


Apply CSP Focus Membership to see full report


Project Participants

 

Developer and investor: Beijing Shouhang IHW Resources Saving Technology Company Ltd (Shouhang)

In 2014, Shouhang started commercialized CSP project development and entered into scale industry stage. Shouhang devotes into systematic R&D of concentrator system, receiver, thermal energy storage system, heat exchange system and thermal electricity integration control system. By now, Shouhang successfully achieved small and middle size testing systems for tower, Parabolic Trough and dish CSP projects.

Apply CSP Focus Membership to see full report

                                             

 Plant photos


Leave your thoughts here

Latest News

See more+
  • Dubai’s concentrated solar power project starts supplying electricity to the grid

    On November 29 (Dubai Time), the Trough Unit No. 1 facility of Shanghai Electric’s 700MW solar thermal and 250MW photovoltaic solar power plant in Dubai has successfully achieved grid-connected electricity generation, marking a significant milestone along the path of the firm’s entry into the renewable energy sector. The facility is already delivering top-notch technical parameters and reliable

  • Four bidders shortlisted for 200MW solar plant

    The plant, which will use lenses or mirrors to focus a large area of sunlight onto a receiver, is due to be operational by 2027 and is the flagship renewable project in government’s Integrated Resources Plan (IRP) for energy development in the years to 2040.On Tuesday, the Ministry of Minerals and Energy published a shortlist of four bidders who include major global players with thousands of mega

  • CSP Project Tenders Last Week (Nov.14-20)

    Project Construction Supervision Bidding- POWERCHINA Ruoqiang 100MW CSP + 900MW PV ProjectOn Nov. 14, POWERCHINA Renewable Energy Co., Ltd issued a tender announcement for the construction supervision of the POWERCHINA Ruoqiang 100MW CSP + 900MW PV Project. According to the announcement, the owner of POWERCHINA Ruoqiang 100MW CSP + 900MW PV Project is POWERCHINA Ruoqiang Ruida Energy Development C

  • CSP Project Tenders Last Two Week (Nov. 1-13)

    Vacuum Pump Tender- Akesai Huidong New Energy CSP + PV Pilot ProjectOn November 7, East China Electric Power Design Institute Co., Ltd. of China Power Engineering Consulting Group issued a procurement announcement for vacuum pumps for the Akesai Huidong New Energy CSP + PV Pilot Project.Latest Milestone- Akesai Huidong New Energy CSP + PV Pilot ProjectAccording to the Aksai County Government, the

Reports(Member Only)

See more+

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news