Liddell Power Station

<BACK

NO.1-1-3


Novatec’s 9 MWth solar boiler acts as a fuel-saver by feeding steam into the existing coal fired power station and reducing the coal required to operate the facility. The replacement of coal by the solar boiler will cut greenhouse gas emissions by approximately 5,000 tonnes per annum.

                              

Project Overview
Project Name:Liddell Power Station
Country:Australia
Location:Liddell (New South Walles)
Owner(s):Macquarie Generation (100%)
Technology:Linear Fresnel reflector
Turbine Capacity:Net: 9.0 MW Gross: 9.0 MW
Status:Operational
Start Year:2012

                                                                                                                                                                

Background
Technology:Linear Fresnel reflector
Status:Operational
Country:Australia
City:Liddell
Region:New South Walles
Lat/Long Location:32°22′ 34.0″ South, 150°58′ 48.0″ East
Electricity Generation:13,550 MWh/yr
Generation Data Explanation:thermal megawatts-hour
Break Ground:2011/1/1
Start Production:2012/10/1
Project Type:Commercial
Incentives:$9.25 million from the NSW Government Climate Change Fund  Renewable Energy Development Program
Participants
Developer(s):Novatec Solar
Owner(s) (%):Macquarie Generation (100%)
EPC Contractor:Novatec Solar
Operator(s):Macquarie Generation
Generation Offtaker(s):Australian National Electricity Market
Collector Manufacturer  (Model) :Novatec Solar (Nova-1)
Mirror Manufacturer :Novatec Solar
Receiver Manufacturer :Novatec Solar
Solar Field
Solar-Field Aperture Area:18,490 m²
# of Lines:4
Line Length:403 m
Collector Description:Fresnel
Heat-Transfer Fluid Type:Water/Steam
Solar-Field Inlet Temp:140°C
Solar-Field Outlet Temp:270°C
Power Block
Turbine Capacity (Gross):9.0 MW
Turbine Capacity (Net):9.0 MW
Turbine Description:The 9 MWth solar boiler feeds steam into the existing 2000 MW  coal-fired power station
Power Cycle Pressure:55.0 bar
Cooling Method:Dry cooling
Cooling Method Description:Air-cooled condensers
Design-Point Conditions:270ºC, 55 bar, 9.3 MWth peak thermal output
Thermal Storage
Storage Type:None


*Reference from NREL

More from CSP Focus

Next

Latest News

See more+
  • What we've known about Indian CSP tender in Q1 2024

    It was reported that India will carry out a round of renewable energy bidding in the first quarter of 2024, which requires bidders to submit a program must contain more than 50% of the CSP capacity. This news got great attention in the past weeks on the possibility of CSP revival in India. But how about the challenges to hinder the development of Indias solar thermal power generation in the past y

  • CSP Project Tenders Last Week (Apr.15-21)

    Procurement and Construction Bidding- Xinhua Hydropower Bozhou 100MW CSP ProjectOn April 17, Xinhua Botai (Bole) Power Investment Co., Ltd. issued a bidding announcement for Xinhua Hydropower Bozhou 100MW CSP+900MW PV Project bid section VII: 100 MW CSP project PC general contracting. Bidding document acquisition time: from April 17, 2023 to April 24, 2023 at 16:00.One step closer towards Australi

  • One step closer towards Australia’s first commercial scale concentrated solar power plant

    On behalf of the Australian Government, the Australian Renewable Energy Agency (ARENA) has announced it has approved $65 million in funding to Vast Solar to construct VS1, a first-of-a-kind 30 MW / 288 MWh concentrated solar power (CSP) plant in Port Augusta, South Australia.ARENA’s funding for VS1 is conditional upon the project reaching financial close, which is targeted to occur in late 2023.

  • CSP Project Tenders Last Week (Apr.8-14)

    EPC Tender- SPIC Shanshan 100MW CSP ProjectOn April 8, SPIC Henan Company issued a public bidding announcement for the EPC general contract of SPIC Shanshan 100MW CSP Project. Application deadline: April 14, 2023, 23:59.Olympic Brewery: Paving the way for beer production by harnessing solar energy, in partnership with AbsoliconAthens, March 4, 2023 - In the framework of its ESG strategy with the k

Reports(Member Only)

See more+
  • CSP Focus Membership Proposals

    We are now proposing CSP Focus Membership, hoping to better serve our members to keep pace with the latest updates of ongoing CSP projects worldwide, and to establish and maintain business relations with major shareholders of the projects. CSP Focus offers to Membership exclusive access to:1. Daily/Weekly update and analysis on CSP policies, projects, technologies, market trend and corporate relea

  • The Latest CSP Focus Monthly Update

    Join CSP Focus Membership to Get the Latest CSP Focus Monthly Update December Edition.

  • CSP Project Monthly Update 2022 December Edition

    CSP Focus is presenting CSP Project (China) Update 2022 December Edition.Detail report is available for CSP Focus Membership.

  • Presentations-CSP Focus China 2021

    The Report is for CSP Focus Members only.

Upcoming Events

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news