Yumen Xinneng 50MW Molten Salt Tower Beam-down CSP Project

<BACK

2018-8-8


 Project Schedule

 

● June, 2018, No.1 Modulecompleted, heliostats installation finished.

● April, 2018, steam turbinefoundation started, and No.2-5 modules started construction.

● Dec.7, molten salt thermalelectricity storage system started construction.

Dec. 4, 2017, heat exchanger bidders announced & steam generator bidding restarted.               

● Nov. 28, 2017, molten salt bidding opened.

● 2017, the first solar collectingsystem module commissioning to be finished.

● 2017, 3 solar collecting system modulesconstruction and equipment installation to be completed.


  Progress expectation:


● Aug.30, 2018, 15 heliostats of solar collectingsystem module installed

● Sept.15, 2018, storage system installation andcommissioning finished

● Nov.1, 2018, a complete set of generator to bestarted

● Nov.15, 2018, connected to the grid for the firsttime

● Dec.31, 2018, put into operation


  Full report view online


 Project Overview


Yumen Xinneng 50MW molten salt tower CSP plant was officially selected as one of China 1st batch of CSP pilot projects in September 2016. With total investment of RMB 1.78 billion, the project is expected to be completed in 2 years. The project is located in Zhengjiashawo CSP Park, 5km far from new downtown of Yumen city, Gansu Province. The 50MW project takes beam-down CSP technology with 15 mirror field modules, and one 9-hour molten salt thermal storage system & steam turbine set. The annual generating capacity is under load of 4328 hours. The project broke ground in July 2017, and is expected to be finished by December, 2018.

As recognized by CSP industry players, the Direct Normal Irradiance (DNI) should be above 1,700kW.h/㎡, and the DNI in Yumen is around 1,901 kW.h/㎡, indicating that Yumen is rich in solar resources and a great place for building CSP plants.

           

Basic information

Location

Zhengjiashawo CSP Park

Capacity

50MW

Investment

1.78 billion

Annual generating capacity

4328h

Thermal energy stroage hours

9h


Project Participants

 

China Sinogy Electric Engineering Co., Ltd (CSECC) signed a RMB 1.613 billion EPC contract with Yumen Xinneng in May, 2017, and set up project department in June, 2017.

With years of accumulation, CSECC, an affiliated company of Thvom has strong competitive advantages in business qualification, engineering design, technical services, project experience, and talented specialist team. CSECC possesses Class A credentials of engineering design, engineering consulting and engineering investigation.  

Main participants and biding situation:

                                                                                                                                                                                                                              

NO.

Equipment/Service

Supplier/Candidate

1

Steam turbine

Shanghai Electric--Shanghai Turbine  Works Co., Ltd.

2

Generator

Shandong Jinan  Power Generation Equipment Factory

3

Steam generator

Dongfang Boiler

4

Air cooling  equipment

Shanghai  Electric SPX Tech & Engineering Co., Ltd

5

Molten salt pump

Flowserve; Ruhr Pumpen;  Sulzer

6

Feedwater pump

KSB; Sulzer;
ZHENGZHOU POWER EQUIPMENT WORKS

7

Heliostat

Jiangsu XinChen CSP Technology Co., Ltd

8

Beam down tower

Jiangsu XinChen CSP Technology Co., Ltd

9

Central receiver

Jiangsu XinChen CSP Technology Co., Ltd

10

Molten salt storage tank

Jiangsu XinChen CSP Technology Co., Ltd

11

EPC

China Sinogy Electric Engineering Co., Ltd

12

 

Supervisor

Anhui Energy  Construction Engineering Supervision Co., Ltd

13

 

Field leveling  & Temporary

construction

Gansu No.1 Construction  Group

 

14

Main workshop  construction

Anhui Power  Construction No.1 Engineering Co., Ltd

15

Power Block  Construction &

Installation

JEPC3-China  Energy Engineering Group Jiangsu No.3 Electric

Power Construction Co., Ltd.

16

 

Solar collection  & Thermal

storage system

Jiangsu XinChen  CSP Technology Co., Ltd

 

17

Owner's Engineer

Shanghai Parasol  Renewable Energy Company

18

 

Turnkey EPC of  Central Storage

Tank

China Chengda  Engineering Co., Ltd.

19

Operator &  Owner

Yumen Xinneng  CSP No.1 Power Co., Ltd.

                                                                                            

 Plant photos


More from CSP Focus

Next

Latest News

See more+
  • Italy plans 50 GW PV, 18.4 GW wind to meet 2030 target

    January 14 (Renewables Now) - Italy will aim to reach 50 GW of solar photovoltaic (PV) capacity at end-2030 under its new climate and energy plan, the target for wind is 18.4 GW.Last week the Ministry of Economic Development (MISE) presented Italy’s National Integrated Plan for Climate and Energy 2030, which contains details on the future expansion of renewable energy in order to reach a 30% shar

  • Italy sets 2030 solar target of 50 GW

    The Italian government has published a plan for climate and energy envisaging a central role for solar in the nation’s energy mix, with PV expected to represent more than the half the power generation capacity from renewables by the end of the next decade.The Italian government has fleshed out its plans for solar up to the year 2030Image: Octopus EnergyItaly’s Ministry of Economic Development (M

  • Analysis of Cerro Dominador, the first Concentrated Solar Power plant in Chile

    Cerro Dominador project is a 210MW hybrid concentrated solar power (CSP) and photovoltaic (PV) power complex under construction on a 1,000ha-site, approximately 60km away from Calama at Maria Elena in the Atacama Desert, Chile.Construction on the $1.4bn project, which consists of a 100MW PV plant and 110MW CSP plant, was started in 2014.The PV plant was commissioned in February 2018, while the Cer

  • Cerro Dominador was distinguished by Project Finance International for its financing

    January 11th., 2019. Cerro Dominador has been distinguished by Project Finance International as the Best Renewable Energy Financing in the Americas.The financing of the first thermal solar plant in Latin America for an amount exceeding USD 800 million was signed last may by a group of international and local financial institutions, including Natixis, Deutsche Bank, Société Géné

Free Reports

See more+
  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Overview of Saudi Arabia's Renewable Energy Program 2030

    Saudi Arabia significantly increased its renewable energy targets and long term visibilityMEIM and PIF are working on complemenrary tracks to promote localization of manufacturing5 wind and 3 solar segments can potentially be localized in the short to medium term in KSAProjects will be deployed in 35+ parks spead across the KingdomParks are being pre-developed to boost projects bankability and ex

  • China 1st Batch of CSP Pilot Projects Update

    Nov-2018 Edition Part 1: Background and Fact Sheet(P1) 1.1 Technologies of China CSP Pilot Projects (P2) Chart 1: Technologies of China CSP Pilot Projects (P3) 1.2 Locations of China CSP Pilot Projects (P5) Chart 2: Locations of China CSP Pilot Projects (P6) 1.3 Ownership of China CSP Pilot Projects (P7) Chart 3: Ownership of China CSP Pilot Projects (P8) 1.4 Developer, EPC Contractor and Technology Provider (P9) Chart 4: Developer, EPC Contractor and Technology Provider of China CSP Pilot Projects (P10)

  • SUPCON Delingha 50MW Molten Salt Tower CSP Project

    As one of the first batch of CSP pilot projects in China, Supcon Solar Delingha 50MW Tower CSP Project is located in Delingha city of Qinghai Province. With 50MW installed capacity and 7 hours TES system, this molten salt tower CSP plant will produce 146GWh electricity every year. The project was completed and connected to the grid on Dec.30, 2018.Updating--Jan., 2019 Edition1. Overview (P2)2. Fa