Yumen Xinneng 50MW Molten Salt Tower Beam-down CSP Project

<BACK

2018-8-8


 Project Schedule

 

● June, 2018, No.1 Modulecompleted, heliostats installation finished.

● April, 2018, steam turbinefoundation started, and No.2-5 modules started construction.

● Dec.7, molten salt thermalelectricity storage system started construction.

Dec. 4, 2017, heat exchanger bidders announced & steam generator bidding restarted.               

● Nov. 28, 2017, molten salt bidding opened.

● 2017, the first solar collectingsystem module commissioning to be finished.

● 2017, 3 solar collecting system modulesconstruction and equipment installation to be completed.


  Progress expectation:


● Aug.30, 2018, 15 heliostats of solar collectingsystem module installed

● Sept.15, 2018, storage system installation andcommissioning finished

● Nov.1, 2018, a complete set of generator to bestarted

● Nov.15, 2018, connected to the grid for the firsttime

● Dec.31, 2018, put into operation


  Full report view online


 Project Overview


Yumen Xinneng 50MW molten salt tower CSP plant was officially selected as one of China 1st batch of CSP pilot projects in September 2016. With total investment of RMB 1.78 billion, the project is expected to be completed in 2 years. The project is located in Zhengjiashawo CSP Park, 5km far from new downtown of Yumen city, Gansu Province. The 50MW project takes beam-down CSP technology with 15 mirror field modules, and one 9-hour molten salt thermal storage system & steam turbine set. The annual generating capacity is under load of 4328 hours. The project broke ground in July 2017, and is expected to be finished by December, 2018.

As recognized by CSP industry players, the Direct Normal Irradiance (DNI) should be above 1,700kW.h/㎡, and the DNI in Yumen is around 1,901 kW.h/㎡, indicating that Yumen is rich in solar resources and a great place for building CSP plants.

           

Basic information

Location

Zhengjiashawo CSP Park

Capacity

50MW

Investment

1.78 billion

Annual generating capacity

4328h

Thermal energy stroage hours

9h


Project Participants

 

China Sinogy Electric Engineering Co., Ltd (CSECC) signed a RMB 1.613 billion EPC contract with Yumen Xinneng in May, 2017, and set up project department in June, 2017.

With years of accumulation, CSECC, an affiliated company of Thvom has strong competitive advantages in business qualification, engineering design, technical services, project experience, and talented specialist team. CSECC possesses Class A credentials of engineering design, engineering consulting and engineering investigation.  

Main participants and biding situation:

                                                                                                                                                                                                                              

NO.

Equipment/Service

Supplier/Candidate

1

Steam turbine

Shanghai Electric--Shanghai Turbine  Works Co., Ltd.

2

Generator

Shandong Jinan  Power Generation Equipment Factory

3

Steam generator

Dongfang Boiler

4

Air cooling  equipment

Shanghai  Electric SPX Tech & Engineering Co., Ltd

5

Molten salt pump

Flowserve; Ruhr Pumpen;  Sulzer

6

Feedwater pump

KSB; Sulzer;
ZHENGZHOU POWER EQUIPMENT WORKS

7

Heliostat

Jiangsu XinChen CSP Technology Co., Ltd

8

Beam down tower

Jiangsu XinChen CSP Technology Co., Ltd

9

Central receiver

Jiangsu XinChen CSP Technology Co., Ltd

10

Molten salt storage tank

Jiangsu XinChen CSP Technology Co., Ltd

11

EPC

China Sinogy Electric Engineering Co., Ltd

12

 

Supervisor

Anhui Energy  Construction Engineering Supervision Co., Ltd

13

 

Field leveling  & Temporary

construction

Gansu No.1 Construction  Group

 

14

Main workshop  construction

Anhui Power  Construction No.1 Engineering Co., Ltd

15

Power Block  Construction &

Installation

JEPC3-China  Energy Engineering Group Jiangsu No.3 Electric

Power Construction Co., Ltd.

16

 

Solar collection  & Thermal

storage system

Jiangsu XinChen  CSP Technology Co., Ltd

 

17

Owner's Engineer

Shanghai Parasol  Renewable Energy Company

18

 

Turnkey EPC of  Central Storage

Tank

China Chengda  Engineering Co., Ltd.

19

Operator &  Owner

Yumen Xinneng  CSP No.1 Power Co., Ltd.

                                                                                            

 Plant photos


More from CSP Focus

Next

Latest News

See more+
  • CSP Focus China 2019 will see you on Mar.21-22 Beijing

    Triumphant news keeps pouring in for 2018 China CSP industry.CGN Solar’s Delingha 50MW PT project has been proclaimed to be commercial operational on October 10, making China the 8th country who owns large-scale CSP technology. Also,2 solar tower projects are expected to be operational by the end of this year. One of them is Shouhang’s 100MW molten salt tower plant. The plant is under commission

  • CSP real-time dispatch model hikes revenues by over 15%

    New software combining dispatch algorithms with probabilistic forecasting could reduce CSP bid prices by a quarter and spur fresh U.S. CSP deployment, Mike Wagner, Principal Investigator at the National Renewable Energy Laboratory (NREL), told New Energy Update.Optimized dispatch of CSP plus storage is set to reduce maintenance costs and increase market revenues. (Image credit: WangAnQui)On Octobe

  • Dubai world's tallest solar tower CSP plant to be fitted with a CMI receiver

    In 2021, a260-meter high solar tower is set to rise in the Emirate of Dubai and, when thethousands of mirrors of its solar field turn to face to its summit, they willlight up a CMI Energy receiver.The Mohammedbin Rashid Al Maktoum solar park,named after the Emir of Dubai, is one of the worlds largest renewable energyprojects and forms part of Dubais ambitious strategic vision of reaching 75%-useof

  • Mohammed bin Rashid Al Maktoum Solar Park adds 250MW to its 4th phase to reach 950MW taking total investment to AED 16 billion

    Dubai Electricity and Water Authority (DEWA) has signed an amendment to the Power Purchase Agreement (PPA) with the consortium led by Saudi Arabia’s ACWA Power for the fourth phase of the Mohammed bin Rashid Al Maktoum Solar Park. The amendment includes adding 250MW of photovoltaic solar panels, at a cost of 2.4 US cents per kilowatt hour, the worlds lowest. With this addition, the total capacity

Free Reports

See more+
  • Applicants in China 2nd Batch of CSP Demonstration Projects

    Sheet1: Projects Applying for China 2nd Batch of CSP DemonstrationsSheet2: Projects Located in Hami Applying for China 2nd Batch of CSP Demonstrations

  • CONCENTRATED SOLAR POWER IN THE MENA REGION

    1. CONCENTRATED SOLAR POWERIN THE MENA REGION 1.1 An introduction to ConcentratedSolar Power (CSP)2. HOW IT WORKS?3. CSP PROJECTSIN THE MENA REGION 3.1 Shams 1 Project 3.2 Noor Ouarzazate & Noor Midelt4. CHALLENGES TO DEPLOYMENT 4.1 Project Costs and Supply Chain 4.2 Lack of Funding to Support R&D 4.3 Financing and Project Risk5. HOW TO OVERCOME THESE CHALLENGES?6. WHAT DOES THEFUTUR

  • Abengoa CSP Technology Experience in China Market

    1. Introduction: Abengoa at a glance2. STE Abengoa References: Main Achievements3. CSP LCOE Evolution: STE LCOE Evolution main relevant countries4. EPC cost in a STE power plant 4.1 Tower technology 4.2 Parabolic trough technology5. Specific cases and scheme for Abengoa in China 5.1 Haixi Luneng Molten Salts Tower Technology 50 MWe, Qinghai 5.2 Yumen East Town Parabolic Trough Technology 50 MW

  • Power Output Reduction Caused by Equipment Accidents —Supcon 10MW&50MW CSP Tower Plant Case Study

    ● Analysis of impacts on LCOE for STE plants ● Analysis of impact factors on production of SUPCON Delingha 10MW plant ● Plan and progress of SUPCON 50MW CSP demonstration project