Luneng Haixi 50MW Molten Salt Tower CSP Project

<BACK

   2022-7


Project Schedule

 ● 2016-12-26, Project approval from National Energy Administration

 ● 2017-6-30, Project construction started

 ● 2018-3-20, Construction of Receiver Tower Foundation Started

 ● 2018-10, COD of PV and Wind projects

 ● 2018-11-21, Construction completion of receiver tower (147.4m of 181.1m)

 ● 2019-1-2, Civil work completed, equipment installation started

 ● 2019-2-28, Installation of Receiver Supporting Sturcture Started

 ● 2019-4-30, 2,100 heliostats installed (4,400 in total)

 ● 2019-6-6, Installation of Receiver Supporting Sturcture Completed

 ● 2019-7-4, Steam turbine and generator installed

 ● 2019-8-15, Salt Melting Started

 ● 2019-9-5, Grid connection acceptance

 ● 2019-9-19, Grid Connected Successfully

 ● 2020-8-27, 120 Hour Reliability Operation Passed


Full report (Member Only)


Project Overview


With total capacity of 700MW, Luneng Haixi Geermu Multi-energy Complement Integration Optimization Pilot Project consists of 200MW PV, 400MW Wind, 50MW CSP and 50MW energy storage system. 


The annual electricity generation is expected to be around 1262.5GWh after completion of the project, reducing standard coal consumption of 401,500 metric ton and dust emission of 5431.96 metric ton. The CSP plant is normally named Luneng Haixi 50MW Molten Salt Tower CSP Project, consisting of one 188m receiver tower, 4,400 heliostats, 12h thermal electricity storage system. 


The CSP project is expected to be operational before August 30th, 2019.


Apply CSP Focus Membership to see full report


Project Participants

   

Apply CSP Focus Membership to see full report

                                                                                                                                                              

 Plant photos






Latest News

See more+
  • Shams Concentrated Solar Power: Ten years of renewable energy, reducing emissions

    The Shams Concentrated Solar Power planr in the Al Dhafra Region will enter a new decade after a series of successes, underscoring the UAE’s leadership in renewable environmentally-friendly energy, and coinciding with the Year of Sustainability and the preparations to host COP28 in November 2023.Ten years after its establishment, the concentrated solar power station continues to play a leading ro

  • CSP Project Tenders Last Week (Mar.11-17)

    SEPCO3 and BAOWU signed the EPC contract of Tibet Zabuye Integrated Energy Supply ProjectMarch 9, SEPCO3 and Baowu Clean Energy Co., Ltd. signed an EPC contract for the Tibet Zabuyeyuan Integrated Energy Supply Project in Shanghai. Qian Feng, Chairman of Baowu Qingneng Company; Wang Li, Secretary of the Party Committee and Chairman of the Board of SEPCO 3, and Liu Jiang, General Manager of CSNP at

  • CSP Project Tenders Last Week (Mar.4-10)

    Molten Salt Trough Collector Joint Connection Test Platform will be Built in Ali TibetOn March 6, POWERCHINA Zhongnan Engineering Corporation Limited released the public announcement of the procurement results of the molten salt trough collector joint connection test platform for CGN Ali 50MW CSP & 100MW PV Project, whose winning supplier is Hunan Industrial Equipment Installation Co., Ltd.Pre

  • CSP Project Tenders Last Week (Feb.27-Mar.3)

    More Detail project report is available for CSP Focus Membership(Click to Apply). About CSP FocusHaving been devoting to CSP industry since 2011, CSP Focus is honored to witness the progress of global CSP markets. Based in one of the most promising CSP markets— China, and foot printed in other regions like Europe, USA, India, Middle East and Africa. CSP Focus is specialized in organizing top-le

Reports(Member Only)

See more+

Upcoming Events

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news