Power China Gonghe 50MW Molten Salt Tower CSP Project

<BACK

   2022-7


Project Schedule


  • 2015-8,Pre-Feasibility Study Completed

  • 2015-9,Project Company Registered

  • 2015-10-28,Project Registerd

  • 2015-11,Pilot Project Application

  • 2016-9-23,Selected as Pilot Project

  • 2016-11-29,Feasibility Study Evaluation and Inspection Meeting held in Beijing

  • 2017-6-18,Groundbreaking

  • 2018-3-6,Project Construction Started

  • 2018-4,Foundation of Receiver Tower Completed

  • 2018-6-28,On-site Installation of First Heliostat Completed

  • 2018-9-18,Receiver Tower Sealed Atop

  • 2018-11-22,Receiver Tower Concreting Completed

  • 2018-12-1,Generator Stator Installed

  • 2019-1-11,First Receiver Plate Installed

  • 2019-1-14,Heliostat Manufacturing Completed

  • 2019-5-13,Installation of Salt Tank Completed

  • 2019-5-15,Installation of Steam Turbine Completed

  • 2019-9-10,Grid Connection Acceptance

  • 2019-9-18,Steam Turbine Roll-up

  • 2019-9-19,Grid Connection

  • 2020-11-6,Operation in Full Capacity

  • 2020-11-28,240 Hour Continous Operation Test Passed

  • 2021-4-22,Demonstration Project Acceptance

Full report (Member Only)


Project Overview


Locatedin Hainan Eco Solar Energy Park, 12km southwest to Gonghe County of Qinghai Province, Power China Gonghe 50MW Molten Salt Tower CSP Project is selected as one of the first batch of pilot CSP projects in China. With strong support and commitment from the group company - Power China, the projectis under progress and supposed to be commissioned in mid 2019.


Apply CSP Focus Membership to see full report


Project Participants

Apply CSP Focus Membership to see full report

                                                                                                          

 Plant photos



Latest News

See more+
  • Shams Concentrated Solar Power: Ten years of renewable energy, reducing emissions

    The Shams Concentrated Solar Power planr in the Al Dhafra Region will enter a new decade after a series of successes, underscoring the UAE’s leadership in renewable environmentally-friendly energy, and coinciding with the Year of Sustainability and the preparations to host COP28 in November 2023.Ten years after its establishment, the concentrated solar power station continues to play a leading ro

  • CSP Project Tenders Last Week (Mar.11-17)

    SEPCO3 and BAOWU signed the EPC contract of Tibet Zabuye Integrated Energy Supply ProjectMarch 9, SEPCO3 and Baowu Clean Energy Co., Ltd. signed an EPC contract for the Tibet Zabuyeyuan Integrated Energy Supply Project in Shanghai. Qian Feng, Chairman of Baowu Qingneng Company; Wang Li, Secretary of the Party Committee and Chairman of the Board of SEPCO 3, and Liu Jiang, General Manager of CSNP at

  • CSP Project Tenders Last Week (Mar.4-10)

    Molten Salt Trough Collector Joint Connection Test Platform will be Built in Ali TibetOn March 6, POWERCHINA Zhongnan Engineering Corporation Limited released the public announcement of the procurement results of the molten salt trough collector joint connection test platform for CGN Ali 50MW CSP & 100MW PV Project, whose winning supplier is Hunan Industrial Equipment Installation Co., Ltd.Pre

  • CSP Project Tenders Last Week (Feb.27-Mar.3)

    More Detail project report is available for CSP Focus Membership(Click to Apply). About CSP FocusHaving been devoting to CSP industry since 2011, CSP Focus is honored to witness the progress of global CSP markets. Based in one of the most promising CSP markets— China, and foot printed in other regions like Europe, USA, India, Middle East and Africa. CSP Focus is specialized in organizing top-le

Reports(Member Only)

See more+

Upcoming Events

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news