Concentrated Solar Power puts end to Morocco electricity blackouts

2018.01.10     From: CSP Today

Morocco’s first operating CSP plant has shown that concentrating solar power can solve the problem of energy blackouts in the peak evening hours, a senior representative of the Moroccan Agency for Sustainable Energy (MASEN) told the recent CSP Seville conference.


The 160 MW Noor 1 parabolic trough power plant exceeded its objectives in year one and brought stability to the grid, according to Abdelkader Himdi, Director of Operations and Maintenance at MASEN. The region around Noor 1 has seen a “drastic improvement on the quality of service, there are no more blackouts with Noor 1 operating,” he said.


The Ouarzazate CSP complex at the junction of the Atlas Mountains and Sahara Desert will be the largest CSP complex in the world upon completion. Noor 2 and Noor 3, the second and third phases, will have 200 MW and 150 MW capacity respectively. Noor 1 has three hours thermal energy storage. Noor 2, also based on parabolic trough technology, will have six hours storage, and Noor 3, with its 250m power tower, will have seven-and-a-half hours storage. Noor 1 provides electricity for 115,000 homes, and Noor 2 and 3 are expected to provide for an additional 280,000 homes.


Morocco, with a population of 35 million people, has set what Himdi called “very aggressive” renewables objectives. It aims to have 42% of installed energy capacity coming from renewables by 2020, and for this to increase to 52% by 2030. MASEN was established in 2013 to develop and manage 2,000 MW of solar power plants.


The government does “not care” which technologies go into making up the overall renewables mix, and is focused only on solutions to Morocco’s problems of being overly reliant on the importation of fossil fuels, Himdi said.


Getting the storage right


Sergio Relloso, Performance Guarantee Manager at SENER, EPC partner to all three phases of the Ouarzazate project, said one of the main lessons to come out of Noor 1 was the need to have at least six storage hours built into the plants. The tender for Noor 1 required that the joint venture partners – SENER, along with Saudi Arabia’s ACWA and fellow Spanish firms TSK and Acciona – implement only three hours storage. At Noor 2 and Noor 3, the designers were free to decide how much storage they wanted.


Typical peak load hours are 7pm to midnight in summer, and 5-10pm in winter, he said. “There are no issues in summer, because we have plenty of energy. But in winter, it’s the turbine component that adapts to the variations in output from the solar field.”


Relloso said SENER’s projects in Spain produce at a maximum load and the storage absorbs the variation from the solar field. In Morocco, he said, they had to adapt their strategy to maximize production during peak time.


At Noor, “we charge at full load, maximum charging rate from storage, as much as we can, and the rest of the energy that the storage cannot admit goes to to the turbine; the turbine absorbs the variations of the solar field. It’s the output of the tower that absorbs the variations… This is a clear example of how the plant can adapt to provide energy inside peak hours,” Relloso said.


Ouarzazate consists of Noor 1 (left), Noor 2 (center), and Noor 3 (right). (Image credit: SENER)


Becoming energy independent


The Climate Investment Funds provided $435 million in concessional financing for Ouarzazate. This was then used to leverage more than $3 billion from other financing institutions including the World Bank Group and the African Development Bank (AfDB). Last month, the AfDB committed an additional $265 million to the development of the Noor projects.


Stratos Tavoulareas, Senior Energy Advisor International Finance Corporation, who spoke on general terms about concessional financing to the Seville conference, said developing countries should accept such financing for the first three to four projects. Later, once it is established that CSP or other renewables technologies can stand on their own, a country should no longer apply for such financing, he said.


Electricity generated by Noor 1 costs $240/MWh, reduced to $180/MWh when factoring in concessional financing, ACWA Power’s Paddy Padmanathan has previously stated. Noor 2 will produce at a significantly lower cost than Noor 1: $190/MWh before factoring in concessional financing.


In Seville, Himdi admitted the price was still high, and said the challenge is to ensure that reducing costs is not a one-off, but can be done in a more consistent way to bring costs to parity with the global average or better.


Tavoulareas and Relloso also described the benefits these projects have for the local population. Ouarzazate is a remote and poor area, even by Moroccan standards, where GDP per capita across the country is less than $3,000 per person. At Noor 1, 70-80 people are employed in operations and maintenance, and an additional 50 in other direct employment such as security, cleaning and temporary maintenance. In preparation for Noor 2 and Noor 3, SENER and the authorities have an agreement to train locals. At Noor 1, 30% of people employed at the plant are locals; at Noor 2 and Noor 3, the target is 35%.


“This is a tricky subject. We can’t just impose and say you need a minimum,” he said. “What we have been trying to do is prepare local companies to be able to catch the opportunities created by these projects. There is some work to be done with local companies, and also to encourage the EPC developers to help these companies take part in the project and have the maximum impact.”


Relevant conference: CSP Focus China 2018, Beijing, China, March 22-23th

Leave your thoughts here

Free Reports

See more+
  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Overview of Saudi Arabia's Renewable Energy Program 2030

    Saudi Arabia significantly increased its renewable energy targets and long term visibilityMEIM and PIF are working on complemenrary tracks to promote localization of manufacturing5 wind and 3 solar segments can potentially be localized in the short to medium term in KSAProjects will be deployed in 35+ parks spead across the KingdomParks are being pre-developed to boost projects bankability and ex

  • China 1st Batch of CSP Pilot Projects Update

    Nov-2018 Edition Part 1: Background and Fact Sheet(P1) 1.1 Technologies of China CSP Pilot Projects (P2) Chart 1: Technologies of China CSP Pilot Projects (P3) 1.2 Locations of China CSP Pilot Projects (P5) Chart 2: Locations of China CSP Pilot Projects (P6) 1.3 Ownership of China CSP Pilot Projects (P7) Chart 3: Ownership of China CSP Pilot Projects (P8) 1.4 Developer, EPC Contractor and Technology Provider (P9) Chart 4: Developer, EPC Contractor and Technology Provider of China CSP Pilot Projects (P10)

  • SUPCON Delingha 50MW Molten Salt Tower CSP Project

    As one of the first batch of CSP pilot projects in China, Supcon Solar Delingha 50MW Tower CSP Project is located in Delingha city of Qinghai Province. With 50MW installed capacity and 7 hours TES system, this molten salt tower CSP plant will produce 146GWh electricity every year. The project was completed and connected to the grid on Dec.30, 2018.Updating--Jan., 2019 Edition1. Overview (P2)2. Fa

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:+86-21-6111 0177

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news