Power China Gonghe 50MW Molten Salt Tower CSP Project

<BACK

   2020-1-14


Project Schedule


  September 19th, 2019, successfully connected to the grid  New! 

 ● January 14th2019, heliostat completed 

 ● December 1st, 2018, Generator Stator Installed

 ● November 22nd, 2018, Receiver Tower Concreting Completed

 ● September 18th, 2018, Receiver Tower Sealed Atop

 ● June 28th, 2018, On-site Installation of First Heliostat Completed

 ● June 18th, 2018, Project Construction Started

 ● April, 2018, Foundation of Receiver Tower Completed

 ● November 29th, 2016, Feasibility Study Evaluation and Inspection Meeting

 ● September 23rd, 2016, Selected as Pilot Project

 ● November, 2015, Pilot Project Application

 ● October 28th, 2015, project registerd      

 ● September, 2015, Project Company Registered

 ● August,2015, Pre-Feasibility Study Completed

Full report view online


Project Overview


Locatedin Hainan Eco Solar Energy Park, 12km southwest to Gonghe County of Qinghai Province, Power China Gonghe 50MW Molten Salt Tower CSP Project is selected as one of the first batch of pilot CSP projects in China. With strong support and commitment from the group company - Power China, the projectis under progress and supposed to be commissioned in mid 2019.


Basic Information

Location

Gonghe, Hainan Area, Qinghai Province

Longitude and  Latitude

N36°6′8″E100°37′30″

DNI

~1900kWh//year

Installed Capacity

50MW

Technology

Molten Salt Tower CSP

Storage

6 Hours

Starting Date

2017-6-18

Status

Under Construction

COD

2019 (expected)

Annual Electricity  Generation

156.92GWh (expected)

Annual Operation  Time

3,138 Hours

Total Investment

RMB 1.222 Billion

                                                                 

Project Participants

                                                                                                                

Equipment

Bidders

                                    (Winners are  highlighted)

Solar Field and Receiver
Highest: over RMB 900 Million
Lowest: around RMB 500 Million
Average: around 650 Million

Shanghai  Electric BrightSource Solar Energy Co., Ltd

Beijing Shouhang  IHW Resource Saving Technology Co., Ltd

Beijing Babcock  & Wilcox / Thermal Focus

Zhejiang Supcon  Solar Energy Technology Co., Ltd

Harbin Turbine  Co., Ltd

Power China  Nuclear Engineering Co., Ltd

Molten Salt
Average: Around RMB 52 Million

Qinghai Enesoon  New Material Technology Co., Ltd

Shanghai Salt  Lake Wentong Chemical Co., Ltd

SNM

Jiaocheng  Bingsheng Chemical Co., Ltd

Qinghai Lianda  Chemical Co., Ltd

SGS

Shanghai Boiler  Works, Ltd.

Steam Turbine

Harbin Turbine  Co., Ltd

Air Cooling System

Beijing Shouhang  IHW Resource Saving Technology Co., Ltd

Cold Molten Salt Pump

Flowserve/DIVERSE  ELECTRONICS

Hot Molten Salt Pump

Flowserve/DIVERSE  ELECTRONICS

Salt Drain Pump&Auxiliary Electrical  Equipment

Jiangsu Jinlin  Chemical Machinery Co., Ltd.

Regulating Valve

Flowserve/DIVERSE  ELECTRONICS

Molten Salt Triple Eccentric Butterfly  Valve

Beijing Zhonghui  Datong / OHL

Molten Salt Tank

Power China  Nuclear Engineering Co., Ltd / Power China

Hubei Electric Engineering Co.,  Ltd

Receiver

Hangzhou Boiler  Group

HTF&TES Installation and  Commissioning

Power China  SEPCO1 Electric Power Construction Co., Ltd

Reflecting Mirror

Daming Glass

Linear Motion Actuator

Wuxi HongBa  Mechanical Electrical Equipment Co.,Ltd.

Electric Heater - Molten Salt Tank

Chromalox/Thermal  Focus

Heat Tracing

MICC

Heat Tracing - Molten Salt Piping

Jiusheng  Electric Co., Ltd

DCS

Zhejiang Supcon  Solar Energy Technology Co., Ltd

                                                                                                                                                                                                                              

 Plant photos



Latest News

See more+
  • 10th Annual CSP Focus China 2020 rescheduled on Oct 22-23 in Beijing, real-time online conference available

    10thAnnual CSP Focus China 2020 was postponed to Oct 22-23 in Beijing China, around30 speakers and 200 participants will attend this grand gathering. Andreal-time online conference will be available to those registered delegates whoare not able to join due to travel constraint. Thisconference will highlight:Performance analysis of operating CSP plants in China - 8 plants, 500MW in total;How to res

  • Xavier Lara on How Spain’s Q4 Auction Can Achieve the 5 GW of CSP it Wants

    Ultimate Trough CSP from schlaich bergermann partner sonne GmbH (SBPS) in Dubai(IMAGE@ SBPS)Spain’s National Energy and Climate Plan, the PNIEC (Plan Nacional de Industria, Energia y Clima) includes a desired 5 GW of CSP added to its existing 2.3 GW, with 2.5 GW in a first tranche from 2021 to 2025 and a second 2.5 GW from 2026 to 2027.But what are the policies needed to make this actually happen

  • Sener sells three Concentrated Solar Power plants in Seville and Cádiz to the Qualitas fund

    Q-Energy, the energy investment vehicle of Qualitas Equity (former Fotowatio investor), has bought from Sener and Masdar -subsidiary of Mubadala- the Concentrated Solar Power Torresol Energy Investments S.A. (“Torresol Energy”), owner of three solar thermal plants in Spain with a total capacity of 120 MW located in Seville and Cádiz. The transaction also includes the operating company of th

  • HelioControl Project Completed: Determination and control of aim points for heliostat fields in operation

    Among solar thermal power plants, solar tower systems are considered to have the greatest potential in terms of efficiency and cost reduction. In particular, costs can be saved on mirrors (heliostats), which account for between 30 and 40 percent of the investment. Frequent calibration or control of the heliostat aim points is one approach. In the HelioControl project, the Fraunhofer Institute for

Free Reports

See more+
  • Dubai 950MW NOOR Energy 1 CSP+PV Project

    The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.

  • China Large-scale CSP Projects Update

    Updating--Jan., 2020 Edition24 pagesPart 1: Background and Fact Sheet (P1-11) · Implementation and adjustment of 1st batch of CSP demonstrations· FiT policy update and prediction· Sum-up on the 20 projects technology, location, ownership and key participants Part 2: Milestones of Ch

  • Suppliers List of China Key CSP Projects (Updating)

    13 key concentrated solar power projects in China undergoing:Shouhang Dunhuang 100MW Molten Salt Parabolic Trough ProjectRoyal Tech Yumen 50MW Parabolic Trough ProjectDCTC Dunhuang 50MW MS CLFR ProjectRayspower Yumen 50MW Trough ProjectCNNC Royal Tech Urad 100MW Parabolic Trough ProjectSupcon Delingha 50MW Molten Salt Tower ProjectLuNeng Haixi 50 MW Solar Thermal Tower Plant ProjectPower C

  • Construction and Operation of SUPCON SOLAR Delingha 50MW Tower CSP Project

    40 pages in totalCompany Profile (P3-4)Construction of Delingha 50MW Tower CSP Project (P6-17)Operation of Delingha 50MW Tower CSP Project (P18-30)Issues during Commissioning and Operation (P31-39)