Shanghai Electric completes Noor Energy 1 Concentrated Solar Power tower in Dubai.


Construction partners on the 950 MW Noor Energy 1 Concentrating Solar Power- Photovoltaic project in Dubai completed the 260-meter high receiver tower on January 9, Shanghai Electric, lead EPC contractor, said in a statement.


The $4.4 billion Noor Energy 1 solar thermal project will be the world’s largest CSP plant and includes a 100 MW CSP tower plant, three 200 MW parabolic trough CSP systems, 250 MW of PV capacity and 15 hours of molten salt CSP storage capacity.



Developed by Saudi Arabia’s ACWA Power, the Dubai Electricity Water Authority (DEWA) awarded the project in 2017 at a record-low tariff of $73/MWh.


Global levelized costs for solar, wind in 2010-2022


Source: IRENA’s ‘Renewable power generation costs in 2018’ report (May 2019).


The Noor Energy 1 project reached financial closure in March 2019. The cost will be met through $2.9 billion of debt and $1.5 billion of equity. DEWA is to provide $750 million, half of the project equity. Of the remaining half, ACWA Power will provide 51% and China’s Silk Road Fund 49%. In June 2019, the Silk Road Fund purchased a 49% stake in ACWA Power’s renewable energy business.


The project will include technologies from a wide range of European suppliers as well as U.S. group BrightSource.



The 100 MW CSP tower power plant at Noor Energy 1 is scheduled to be online by October. (Image credit: Shanghai Electric) 


Belgium’s CMI will supply the molten salt receiver for the tower plant and Rioglass will supply the heliostats, while BrightSource will supply the control systems for the tower plant section.


Spain’s Abengoa will supply the parabolic trough systems and Lointek will supply the integrated steam generation system and oil-salt thermal storage system. Germany’s Siemens will supply four steam turbine generators and auxiliary equipment for the parabolic trough and tower plants. Denmark’s Aalborg will supply steam generation technology for the parabolic trough section.


Shanghai Electric is faced with the challenge of minimizing costs while also meeting a demanding construction schedule. The plant will be brought online in phases in 2020-2022 and the first parabolic trough plant and central tower unit are scheduled to be completed by October 2020.



Upcoming CSP events:


10th CSP Focus China 2020 (March.25-26, Beijing China) 

5th CSP Focus MENA 2020(June.23-24,Dubai, UAE)


More CSP news and reports please visit www.cspfocus.cn 

or CSP Focus social media on LinkedInTwitterFacebook.


Leave your thoughts here

Latest News

See more+
  • Magtel launches a hybrid solar power plant that will produce energy at night in Hornachuelos

    The Cordoba-based engineering company Magtel has started the environmental consultation phase of the first hybrid renewable power plant to be proposed in the province of Cordoba. It will have (if it gets the papers) the two available solar technologies, solar thermal and photovoltaic, but it will have a peculiarity. You can create electrical energy at will. When the energy network demands it. Even

  • CSP Project Tenders Last Week (Sept 1-11)

    Equipment Procurement Tenders- CGN New Energy Jilin 100MW CSP ProjectOn September 2, Daan Guangtou Zhongneng CSP Company issued a bidding announcement for the turbine generator set, steam generation system, solar concentration and heat collection system, cold salt pump, hot salt pump and thermoregulation pump of CGN New Energy Jilin 100MW CSP Project.Tender for Turbine Systems-Tibet Mining Zabuye

  • Letlhakane Concentrated Solar Power Plant in Botswana

    The Letlhakane Concentrated Solar Power Plant is a planned 100 MWconcentrated solar power station in Botswana. The owner, developer and operator of this solar power complex will be an independent power producer, whose identity will be revealed when the ongoing open bidding is concluded. Bids were received until June 2022.The power generated here is expected to be bought by Botswana Power Corporati

  • DEWA receives four bids from international companies for sixth phase of solar park

    Dubai Electricity and Water Authority (DEWA) has received 4 bids from international companies for consultancy contract for the sixth phase of the Mohammed bin Rashid Al Maktoum Solar Park, Dubai Media Office (DMO) announced on Tuesday.The single-site solar park is the largest of its kind in the world, using the Independent Power Producer (IPP) model, with a production capacity of 5,000 megawatts b

Reports(Member Only)

See more+

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news