中文  |  ENGLISH

CGN Delingha 50MW Thermal Oil Parabolic Trough project

2022.08.04     From: CSP Focus 光略咨询

   2022-7


 Project Schedule


● 2012-3, Enlisted in ADB Funding Project 2012-2014

● 2012-7-13, MOU with ADB

● 2013-2-5, Project Approval l by Local Government

● 2013-3, Grid Access Approval by Local Grid Company

● 2013-12-2, Project Loan Approved by ADB

● 2014-5, Land Leveling and Site Preparation

● 2015-8, Project Formally Started

● 2016-4, Construction of Heat Transfer and TES Started

● 2016-10-23, Construction of Solar Field Started

● 2017-12, Installation of Steam Turbine Completed

● 2018-4, HTF Injecting Completed

● 2018-7, Salt Melting Completed

● 2018-10-10, Commercial Operation


Full report on this project (Member Only)


 Project Overview


CGN Solar Delingha 50MW parabolic trough CSP plant is among China 1st batch of 20 pilot CSP projects and leading the construction progress. With total investment of RMB 1.938 billion, the project is equipped with 9 hours molten salt thermal energy storage. Once completed, CGN Solar Delingha 50MW parabolic trough CSPplant will be the first commercial parabolic trough project, and the first operational pilot CSP project in China.


Apply CSP Focus Membership to see full report


Project Participants


Apply CSP Focus Membership to see full report


 Plant photos

Leave your thoughts here

Latest News

See more+
  • Dubai’s concentrated solar power project starts supplying electricity to the grid

    On November 29 (Dubai Time), the Trough Unit No. 1 facility of Shanghai Electric’s 700MW solar thermal and 250MW photovoltaic solar power plant in Dubai has successfully achieved grid-connected electricity generation, marking a significant milestone along the path of the firm’s entry into the renewable energy sector. The facility is already delivering top-notch technical parameters and reliable

  • Four bidders shortlisted for 200MW solar plant

    The plant, which will use lenses or mirrors to focus a large area of sunlight onto a receiver, is due to be operational by 2027 and is the flagship renewable project in government’s Integrated Resources Plan (IRP) for energy development in the years to 2040.On Tuesday, the Ministry of Minerals and Energy published a shortlist of four bidders who include major global players with thousands of mega

  • CSP Project Tenders Last Week (Nov.14-20)

    Project Construction Supervision Bidding- POWERCHINA Ruoqiang 100MW CSP + 900MW PV ProjectOn Nov. 14, POWERCHINA Renewable Energy Co., Ltd issued a tender announcement for the construction supervision of the POWERCHINA Ruoqiang 100MW CSP + 900MW PV Project. According to the announcement, the owner of POWERCHINA Ruoqiang 100MW CSP + 900MW PV Project is POWERCHINA Ruoqiang Ruida Energy Development C

  • CSP Project Tenders Last Two Week (Nov. 1-13)

    Vacuum Pump Tender- Akesai Huidong New Energy CSP + PV Pilot ProjectOn November 7, East China Electric Power Design Institute Co., Ltd. of China Power Engineering Consulting Group issued a procurement announcement for vacuum pumps for the Akesai Huidong New Energy CSP + PV Pilot Project.Latest Milestone- Akesai Huidong New Energy CSP + PV Pilot ProjectAccording to the Aksai County Government, the

Reports(Member Only)

See more+

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news