 Project Schedule


● October 10, 2018,fully commercial operation

● June 30, 2018connected to the grid

● December 2017, HTF Island started operation

● December 2017, entering heat transfer oil injection phase and turbine low pressure casingsuccessfully capped

● November 2017, 90% of solar fieldcompleted

● September 2017, turbine generator rotorhoisted into position

● August 31, 2017, factory was successfulin receiving electricity

● June 29, 2016, the main transformer wasinstalled in place

● April 2016, HTF & TES startedconstruction

● July 2014, broke ground officially

● February 2013, approved by the localQinghai Province government

● July 13, 2012, signed MoU withAsian Development Bank on CSP project

● April 2012, CGN solar energy establishedthe experimental base of CSP technology


Full report on this project (Member Only)


 Project Overview


CGN Solar Delingha 50MW parabolic trough CSP plant is among China 1st batch of 20 pilot CSP projects and leading the construction progress. With total investment of RMB 1.938 billion, the project is equipped with 9 hours molten salt thermal energy storage. Once completed, CGN Solar Delingha 50MW parabolic trough CSPplant will be the first commercial parabolic trough project, and the first operational pilot CSP project in China.


Apply CSP Focus Membership to see full report


Project Participants


Apply CSP Focus Membership to see full report


 Plant photos

Leave your thoughts here

Latest News

See more+
  • HERLOGAS Ends SUCCESSFULLY the WORLD'S LARGEST Salt Melting In DUBAI, DEWA CSP - Noor Energy 1 Project in Set 3-4 of PT1.

    In this project HERLOGAS collaborates with Shanghai Electric with the melting process of 560,000 tons of salt and the preheating of the 26 storage tanks, to date HERLOGAS has successfully melted 115,000 tons of salt successfully and preheated 4 salt tanks, This melting process that we have ends SUCCESSFULLY in PT1 Set 3-4.Noor Energy 1 PSC will be implementing the 4th phase of Mohammed bin Rashid

  • ACCIONA Energía celebrates 15-year anniversary of the Nevada Solar One Concentrated Solar Plant

    June 30, 2022. ACCIONA Energía, world leader in renewable energy, celebrates 15 years of operations for its Nevada SolarOne Concentrated Solar Plant (CSP) located in Boulder City, Nevada. The plant generates up to 64 MW per hour, enough to power 12,500 Nevada households on an annual basis, and it removes an estimated92,000 metric tons of CO2 emissions annually. ACCIONA Energía’s Nev

  • Why is nobody talking about concentrated solar power?

    Concentrated solar power has a lot more potential than traditional solar panelsDarmau Lee, UnsplashWhen most of us think about solar power, we picture large black panels made of silicon, unattractively stuck on top of houses. These photovoltaic (PV) solar cells are set to play a key role in the global push to “Net Zero”, and you could be forgiven for thinking that, alongside some wind farms here

  • EPC and Project Supervisor Tendering - Guazhou 700MW CSP+PV+Wind

    June 2022Three Gorges Hengji Nengmai Guazhou 700MW CSP+PV+Wind Project was part of the 1.3GW CSP projects released last year in China. The project feasibility study was reviewed and approved in Feb 2022. The project developer issued the tender of EPC by the end of April and tender Project Supervisor 5th of May.Project HighlightsThe Project is consisting of 200MW PV, 400MW Wind and 100MW CSP, and t

Reports(Member Only)

See more+

Upcoming Events

See more+

Project Updates

See more+

CONTACT US

Tex:

Email:csp@cspfocus.cn


备案/许可证编号为:沪ICP备17051021号

Wechat public platform

Follow CSP Focus for more news